16618 W LORILLARD ST 91344
Certificate Information: 16618 W LORILLARD ST 91344
- Application / Permit
- 20014-20000-05822
- Plan Check / Job No.
- B20VN16784
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 16'-5" X 50'-1" IRREGULAR SHAPED ADDITION AND REMODEL TO (E) SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 11/14/2021
- Issuing Office
- Current Status
- CofO Issued on 7/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2021 | RAPHAEL ROSAS |
| Corrections Issued | 1/18/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 9/20/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 9/21/2021 | APPLICANT |
| Issued | 11/14/2021 | APPLICANT |
| CofO in Progress | 6/30/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 7/8/2025 | RUBEN SALAS |
| CofO Issued | 7/8/2025 | RUBEN SALAS |
| Permit Finaled | 7/8/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Sewer availability | Cleared | 7/19/2021 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 8/12/2021 | ANDRES COVARRUBIAS |
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 9/8/2021 | ABDULLAH SADOZAI |
| Grading Pre-Inspection | Cleared | 11/12/2021 | ALEXANDER HELFER |
Contact Information
| Contractor | Finesse Remodeling & Consulting Inc; Lic. No.: 932094-B | 4600 ARIBA DRIVE TARZANA, CA 91356 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/25/2022 | Approved | MICHAEL TEMPLE |
| Pre-Inspection | 1/25/2022 | Partial Inspection | RAUL OLAGI |
| Sewer | 1/25/2022 | Partial Approval | DEANDRE HOFFMAN |
| Underground Mechanical | 1/25/2022 | Partial Approval | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 1/31/2022 | Approved | DEANDRE HOFFMAN |
| Wood Frame | 3/11/2022 | Corrections Issued | DEANDRE HOFFMAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2022 | Corrections Issued | RAUL OLAGI |
| Sewer | 3/17/2022 | Not Ready for Inspection | RAUL OLAGI |
| Wood Frame | 3/17/2022 | Not Ready for Inspection | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2022 | Partial Approval | JAVIER RAMOS JR |
| Rough-Elec/Plmb/HVAC | 3/21/2022 | Partial Approval | JAVIER RAMOS JR |
| Sewer | 3/21/2022 | Approved | JAVIER RAMOS JR |
| Wood Frame | 3/21/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Rough | 3/29/2022 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 4/4/2022 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2022 | Partial Approval | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 4/4/2022 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 4/7/2022 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 4/7/2022 | Approved | JAVIER RAMOS JR |
| Insulation | 4/7/2022 | Partial Approval | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 4/7/2022 | Approved | JAVIER RAMOS JR |
| Rough-Elec/Plmb/HVAC | 4/7/2022 | Approved | JAVIER RAMOS JR |
| Shower Pan | 4/7/2022 | Approved | JAVIER RAMOS JR |
| Insulation | 4/15/2022 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 5/4/2022 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 7/14/2022 | Approved | DEANDRE HOFFMAN |
| Final | 7/14/2022 | Corrections Issued | DEANDRE HOFFMAN |
| HVAC-Final | 7/14/2022 | Corrections Issued | DEANDRE HOFFMAN |
| PLUMBING-Final | 7/14/2022 | Approved | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 2/7/2023 | Approved | JAVIER RAMOS JR |
| Final | 2/7/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Final | 2/7/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 2/7/2023 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 2/7/2023 | Approved | JAVIER RAMOS JR |
| Final | 6/30/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Green Building Final | 6/30/2025 | Approved | CHRISTOPHER ROJAS |