11376 N DE FOE AVE 91331
Certificate Information: 11376 N DE FOE AVE 91331
- Application / Permit
- 20014-20000-05801
- Plan Check / Job No.
- B20VN16740
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18' X 20' RECREATION ROOM AND ADD 11'-5" X 18' FOR NEW ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(B). ALL WORK PER WFPP.
- Permit Issued
- Issued on 4/20/2022
- Issuing Office
- Current Status
- CofO Issued on 3/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2021 | JENNIFER LEE |
| Corrections Issued | 2/1/2021 | JENNIFER LEE |
| Applicant returned to address corrections | 1/14/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 3/15/2022 | JENNIFER LEE |
| Plan Check Approved | 4/5/2022 | COLIN LOREDO |
| Building Plans Picked Up | 4/6/2022 | APPLICANT |
| Issued | 4/20/2022 | APPLICANT |
| CofO in Progress | 2/23/2023 | ROBERT GOLD |
| Permit Finaled | 3/2/2023 | MICHAEL SMITH |
| CofO Issued | 3/2/2023 | MICHAEL SMITH |
| Permit Finaled | 3/2/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 6/17/2021 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 6/17/2021 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 11/19/2021 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 1/13/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/27/2022 | Corrections Issued | GREGG CUMMINGS |
| Deputy Drilled-In Anchors | 7/7/2022 | Approved | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 7/7/2022 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 7/12/2022 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 7/22/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 7/26/2022 | Corrections Issued | DAVID MATSON |
| PLUMBING-Rough | 7/28/2022 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 8/9/2022 | Approved | MICHEL ABAJAN |
| Gas Test | 8/9/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 8/9/2022 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 8/9/2022 | Approved | MICHEL ABAJAN |
| Rough-Elec/Plmb/HVAC | 8/9/2022 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 8/9/2022 | Partial Approval | MICHEL ABAJAN |
| Insulation | 8/12/2022 | Approved | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 8/12/2022 | Partial Approval | DEANDRE HOFFMAN |
| Drywall Nailing | 8/19/2022 | Approved | GREGG CUMMINGS |
| Shower Pan | 8/19/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Shower Pan | 8/26/2022 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 9/20/2022 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Final | 10/25/2022 | Approved | MICHEL ABAJAN |
| Final | 10/25/2022 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 10/25/2022 | Approved | MICHEL ABAJAN |
| HVAC-Final | 10/25/2022 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 10/25/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 10/25/2022 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 10/25/2022 | SGSOV Not Ready | MICHEL ABAJAN |
| Smoke Detectors | 10/25/2022 | Approved | MICHEL ABAJAN |
| Sewer | 1/23/2023 | Approved | JOHN COLEMAN |
| Final | 2/21/2023 | OK to Issue CofO | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 2/21/2023 | SGSOV Approved | ROBERT GOLD |