11376 N DE FOE AVE 91331

Certificate Information: 11376 N DE FOE AVE 91331

Application / Permit
20014-20000-05801
Plan Check / Job No.
B20VN16740
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18' X 20' RECREATION ROOM AND ADD 11'-5" X 18' FOR NEW ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(B). ALL WORK PER WFPP.
Permit Issued
Issued on 4/20/2022
Issuing Office
Current Status
CofO Issued on 3/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/13/2021 APPLICANT
Assigned to Plan Check Engineer 1/28/2021 JENNIFER LEE
Corrections Issued 2/1/2021 JENNIFER LEE
Applicant returned to address corrections 1/14/2022 RAPHAEL ROSAS
Applicant returned to address corrections 3/15/2022 JENNIFER LEE
Plan Check Approved 4/5/2022 COLIN LOREDO
Building Plans Picked Up 4/6/2022 APPLICANT
Issued 4/20/2022 APPLICANT
CofO in Progress 2/23/2023 ROBERT GOLD
Permit Finaled 3/2/2023 MICHAEL SMITH
CofO Issued 3/2/2023 MICHAEL SMITH
Permit Finaled 3/2/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/17/2021 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 6/17/2021 ADRIAN CASTRO
Construction near power lines Cleared 11/19/2021 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 1/13/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 1/13/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/27/2022 Corrections Issued GREGG CUMMINGS
Deputy Drilled-In Anchors 7/7/2022 Approved MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 7/7/2022 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 7/12/2022 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 7/21/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 7/22/2022 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 7/26/2022 Corrections Issued DAVID MATSON
PLUMBING-Rough 7/28/2022 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 8/9/2022 Approved MICHEL ABAJAN
Gas Test 8/9/2022 Approved MICHEL ABAJAN
Green Building Rough 8/9/2022 Approved MICHEL ABAJAN
MERV13>=Rough 8/9/2022 Approved MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 8/9/2022 Approved MICHEL ABAJAN
Underground Mechanical 8/9/2022 Partial Approval MICHEL ABAJAN
Insulation 8/12/2022 Approved DEANDRE HOFFMAN
Interior/Exterior Lathing 8/12/2022 Partial Approval DEANDRE HOFFMAN
Drywall Nailing 8/19/2022 Approved GREGG CUMMINGS
Shower Pan 8/19/2022 Not Ready for Inspection GREGG CUMMINGS
Shower Pan 8/26/2022 Approved MICHEL ABAJAN
Underground Mechanical 9/20/2022 Partial Approval MICHEL ABAJAN
ELECTRICAL-Final 10/25/2022 Approved MICHEL ABAJAN
Final 10/25/2022 Corrections Issued MICHEL ABAJAN
Green Building Final 10/25/2022 Approved MICHEL ABAJAN
HVAC-Final 10/25/2022 Approved MICHEL ABAJAN
MERV13>=Final 10/25/2022 Approved MICHEL ABAJAN
PLUMBING-Final 10/25/2022 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 10/25/2022 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 10/25/2022 Approved MICHEL ABAJAN
Sewer 1/23/2023 Approved JOHN COLEMAN
Final 2/21/2023 OK to Issue CofO ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 2/21/2023 SGSOV Approved ROBERT GOLD