2413 N ALTMAN ST 90031
Certificate Information: 2413 N ALTMAN ST 90031
- Application / Permit
- 20014-20000-05794
- Plan Check / Job No.
- B20VN16716
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 11'-3" X 24'-8" IRREGULAR SHAPD & ENCLOSE 6'-3" X 24'-8" (E) COVERED PORCH AND REMODEL TO (E) SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/13/2021
- Issuing Office
- Current Status
- CofO Issued on 2/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2021 | RAPHAEL ROSAS |
| Corrections Issued | 1/18/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 2/17/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 3/26/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 4/3/2021 | RAPHAEL ROSAS |
| Issued | 4/13/2021 | APPLICANT |
| Building Plans Picked Up | 4/14/2021 | APPLICANT |
| CofO in Progress | 2/17/2022 | KATHRYN BUTTERWORTH |
| Permit Finaled | 2/23/2022 | DEROLD HAUFF |
| CofO Issued | 2/23/2022 | DEROLD HAUFF |
| Permit Finaled | 2/23/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/4/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 2/4/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2021 | CECILIO NAVARRO |
| ZI | Cleared | 3/5/2021 | LAUREN PADICK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rivera,, Bobby Zulueta; Lic. No.: C77218 | 14703 HELWIG AVE NORWALK, CA 90650 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/18/2021 | Approved | OSVALDO PARAMO |
| Wood Frame | 6/1/2021 | Not Ready for Inspection | RUBEN SALAS |
| PLUMBING-Rough | 6/10/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Wood Frame | 6/10/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Insulation | 6/16/2021 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2021 | Partial Approval | JUSTIN CURTIS |
| ELECTRICAL-Rough | 7/27/2021 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 7/27/2021 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 8/3/2021 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 8/9/2021 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 8/24/2021 | Approved | KATHRYN BUTTERWORTH |
| Green Building Rough | 8/24/2021 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 8/24/2021 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 8/24/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| MERV13>=Rough | 8/24/2021 | Approved | KATHRYN BUTTERWORTH |
| Drywall Nailing | 8/30/2021 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 10/5/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Shower Pan | 10/5/2021 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 1/12/2022 | Corrections Issued | THOMAS LOGRASSO |
| Gas Test | 1/12/2022 | Approved | THOMAS LOGRASSO |
| HVAC-Final | 1/12/2022 | Corrections Issued | THOMAS LOGRASSO |
| MERV13>=Final | 1/12/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Final | 1/12/2022 | Corrections Issued | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 1/12/2022 | SGSOV Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 1/21/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 1/21/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| HVAC-Final | 1/21/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| MERV13>=Final | 1/21/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Smoke Detectors | 1/21/2022 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 1/27/2022 | Approved | KATHRYN BUTTERWORTH |
| Final | 1/27/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| Green Building Final | 1/27/2022 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Final | 1/27/2022 | Approved | KATHRYN BUTTERWORTH |
| MERV13>=Final | 1/27/2022 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 1/27/2022 | Approved | KATHRYN BUTTERWORTH |
| Final | 1/28/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| Final | 2/9/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 2/14/2022 | Partial Approval | KATHRYN BUTTERWORTH |