13624 W EMELITA ST 91401

Certificate Information: 13624 W EMELITA ST 91401

Application / Permit
20014-20000-05748
Plan Check / Job No.
B20VN16603
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 21' X 37'-4" IRREGULAR SHAPED ADDITION AND REMODEL TO (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 4/29/2021
Issuing Office
Current Status
Issued on 4/29/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/31/2020 APPLICANT
Assigned to Plan Check Engineer 1/13/2021 RAPHAEL ROSAS
Corrections Issued 1/16/2021 RAPHAEL ROSAS
Plan Check Approved 4/19/2021 RAPHAEL ROSAS
Building Plans Picked Up 4/20/2021 APPLICANT
Issued 4/29/2021 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 1/28/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 2/11/2021 ADRIAN CASTRO
Low Impact Development Cleared 4/12/2021 IDA MEISAMI-FARD
Roof/Waste drainage to street Cleared 4/13/2021 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/10/2021 Conditional Approval MICHAEL TEMPLE
Footing/Foundation/Slab 9/15/2021 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 9/20/2021 Partial Approval MICHEL ABAJAN
Insulation 9/23/2021 Partial Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 9/24/2021 Partial Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 10/4/2021 Partial Approval RICHARD DOCKUS
ELECTRICAL-Rough 2/3/2022 Corrections Issued RICHARD DOCKUS
PLUMBING-Rough 2/3/2022 Approved RICHARD DOCKUS
ELECTRICAL-Rough 3/14/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 5/3/2022 Corrections Issued RICHARD DOCKUS
Rough-Elec/Plmb/HVAC 5/3/2022 Corrections Issued RICHARD DOCKUS
Deputy Wood Construction 5/4/2022 Conditional Approval MICHAEL TEMPLE
BUILDING-Rough-Frame 5/11/2022 Approved RAUL OLAGI
Green Building Rough 5/11/2022 Approved RAUL OLAGI
HVAC-Rough 5/11/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 5/11/2022 Approved RAUL OLAGI
Insulation 5/25/2022 Corrections Issued ALAN MORELOS
Insulation 6/8/2022 Approved RICHARD DOCKUS
Drywall Nailing 6/24/2022 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 8/16/2022 Approved WILLIAM WREN
Shower Pan 8/16/2022 Approved WILLIAM WREN