7845 N BOTHWELL ROAD 91335
Certificate Information: 7845 N BOTHWELL ROAD 91335
- Application / Permit
- 20014-20000-05746
- Plan Check / Job No.
- B20VN16601
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 14' X 21' ADDITION FOR (N) LIVING ROOM AND BATHROOM TO (E) SFD. ALL WORK PER WFPP.
- Permit Issued
- Issued on 3/5/2021
- Issuing Office
- Current Status
- CofO Issued on 5/20/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/8/2021 | RAPHAEL ROSAS |
| Corrections Issued | 1/10/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 2/18/2021 | RAPHAEL ROSAS |
| Issued | 3/5/2021 | APPLICANT |
| CofO in Progress | 5/13/2021 | VINCENT HANLEY |
| CofO Issued | 5/20/2021 | JOHN JANSON |
| Permit Finaled | 5/20/2021 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/19/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 1/19/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2021 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | California Green Home Solutions; Lic. No.: 1043877-B | 7020 HAYVENHURST AVE STE B VAN NUYS, CA 91406 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 3/23/2021 | Partial Approval | VINCENT HANLEY |
| Footing/Foundation/Slab | 3/23/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 3/23/2021 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 4/12/2021 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2021 | Approved | VINCENT HANLEY |
| Green Building Rough | 4/12/2021 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 4/12/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 4/12/2021 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 4/16/2021 | Approved | VINCENT HANLEY |
| Green Building Rough | 4/16/2021 | Approved | VINCENT HANLEY |
| Insulation | 4/16/2021 | Approved | VINCENT HANLEY |
| Drywall Nailing | 4/22/2021 | Approved | VINCENT HANLEY |
| Insulation | 4/22/2021 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 4/22/2021 | Approved | VINCENT HANLEY |
| Shower Pan | 4/22/2021 | Approved | VINCENT HANLEY |
| Sewer | 4/29/2021 | Approved | VINCENT HANLEY |
| Underground Mechanical | 4/29/2021 | Partial Approval | VINCENT HANLEY |
| Final | 5/13/2021 | OK to Issue CofO | VINCENT HANLEY |
| Green Building Final | 5/13/2021 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 5/13/2021 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 5/13/2021 | Approved | VINCENT HANLEY |