7040 N GARDEN GROVE AVE 91335
Certificate Information: 7040 N GARDEN GROVE AVE 91335
- Application / Permit
- 20014-20000-05742
- Plan Check / Job No.
- B20VN16556
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 31'-4" X 20' IRREGULAR SHAPE ADDITION TO (E) SINGLE FAMILY DWELLING. CONVERT (E) ATTACHED GARAGE TO CARPORT.
- Permit Issued
- Issued on 4/22/2021
- Issuing Office
- Current Status
- CofO Issued on 12/18/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2021 | SERGIO MUNIZ |
| Corrections Issued | 1/19/2021 | SERGIO MUNIZ |
| Quality Review Completed | 2/3/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 3/7/2021 | SERGIO MUNIZ |
| Plan Check Approved | 4/20/2021 | SERGIO MUNIZ |
| Issued | 4/22/2021 | APPLICANT |
| Building Plans Picked Up | 4/26/2021 | APPLICANT |
| CofO in Progress | 12/6/2021 | VINCENT HANLEY |
| CofO Issued | 12/18/2021 | MICHAEL SMITH |
| Permit Finaled | 12/18/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 2/4/2021 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 4/7/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 4/8/2021 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | R L Remodeling Inc; Lic. No.: 885032-B | 22817 VENTURA BLVD #852 WOODLAND HILLS, CA 91364 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/12/2021 | Conditional Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 5/12/2021 | Partial Approval | VINCENT HANLEY |
| Sewer | 5/12/2021 | Approved | VINCENT HANLEY |
| Underground Mechanical | 5/12/2021 | Approved | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 5/13/2021 | Conditional Approval | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 5/18/2021 | Approved | MICHAEL PELHAM |
| Footing/Foundation/Slab | 5/18/2021 | Approved | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 5/19/2021 | Corrections Issued | MICHAEL PELHAM |
| Green Building Rough | 5/19/2021 | Not Ready for Inspection | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 5/20/2021 | No Access for Inspection | VINCENT HANLEY |
| Deputy Reinf. Concrete | 5/21/2021 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2021 | Corrections Issued | STEVEN BACK |
| Deputy Reinf. Concrete | 6/22/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 7/14/2021 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2021 | Approved | VINCENT HANLEY |
| HVAC-Rough | 7/14/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 7/14/2021 | Approved | VINCENT HANLEY |
| HVAC-Rough | 8/4/2021 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 8/16/2021 | Approved | VINCENT HANLEY |
| Green Building Rough | 8/16/2021 | Approved | VINCENT HANLEY |
| Insulation | 8/16/2021 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 8/16/2021 | Partial Approval | VINCENT HANLEY |
| Shower Pan | 8/16/2021 | Approved | VINCENT HANLEY |
| Wood Frame | 8/16/2021 | Approved | VINCENT HANLEY |
| Drywall Nailing | 9/3/2021 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 9/3/2021 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 10/4/2021 | Corrections Issued | VINCENT HANLEY |
| Final | 10/4/2021 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 10/4/2021 | Corrections Issued | VINCENT HANLEY |
| HVAC-Final | 10/4/2021 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Final | 10/4/2021 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 10/4/2021 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 10/4/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 10/14/2021 | No Access for Inspection | VINCENT HANLEY |
| Service/Power Release | 10/14/2021 | No Access for Inspection | VINCENT HANLEY |
| ELECTRICAL-Final | 10/19/2021 | Corrections Issued | DAVID SANDOVAL |
| PLUMBING-Final | 10/19/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| ELECTRICAL-Final | 10/22/2021 | Approved | VINCENT HANLEY |
| Final | 10/22/2021 | Corrections Issued | VINCENT HANLEY |
| Gas Test | 10/22/2021 | Approved | VINCENT HANLEY |
| HVAC-Final | 10/22/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 10/22/2021 | Approved | VINCENT HANLEY |
| Final | 12/6/2021 | OK to Issue CofO | VINCENT HANLEY |
| Green Building Final | 12/6/2021 | Approved | VINCENT HANLEY |