7040 N GARDEN GROVE AVE 91335

Certificate Information: 7040 N GARDEN GROVE AVE 91335

Application / Permit
20014-20000-05742
Plan Check / Job No.
B20VN16556
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
31'-4" X 20' IRREGULAR SHAPE ADDITION TO (E) SINGLE FAMILY DWELLING. CONVERT (E) ATTACHED GARAGE TO CARPORT.
Permit Issued
Issued on 4/22/2021
Issuing Office
Current Status
CofO Issued on 12/18/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/24/2020 APPLICANT
Assigned to Plan Check Engineer 1/14/2021 SERGIO MUNIZ
Corrections Issued 1/19/2021 SERGIO MUNIZ
Quality Review Completed 2/3/2021 OMID HEDAYAT
Applicant returned to address corrections 3/7/2021 SERGIO MUNIZ
Plan Check Approved 4/20/2021 SERGIO MUNIZ
Issued 4/22/2021 APPLICANT
Building Plans Picked Up 4/26/2021 APPLICANT
CofO in Progress 12/6/2021 VINCENT HANLEY
CofO Issued 12/18/2021 MICHAEL SMITH
Permit Finaled 12/18/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/4/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 2/4/2021 JOHN TRIANTAFYLLOS
Low Impact Development Cleared 4/7/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 4/8/2021 JOHN TRIANTAFYLLOS

Contact Information

Contractor R L Remodeling Inc; Lic. No.: 885032-B 22817 VENTURA BLVD #852      WOODLAND HILLS, CA 91364
Engineer Standley,, Craig Erick; Lic. No.: C87675 5330 ZELZAH AVE UNIT 7      ENCINO, CA 91316

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/12/2021 Conditional Approval LILIANA PORTILLO
PLUMBING-Rough 5/12/2021 Partial Approval VINCENT HANLEY
Sewer 5/12/2021 Approved VINCENT HANLEY
Underground Mechanical 5/12/2021 Approved VINCENT HANLEY
Deputy Drilled-In Anchors 5/13/2021 Conditional Approval LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 5/18/2021 Approved MICHAEL PELHAM
Footing/Foundation/Slab 5/18/2021 Approved MICHAEL PELHAM
BUILDING-Rough-Frame 5/19/2021 Corrections Issued MICHAEL PELHAM
Green Building Rough 5/19/2021 Not Ready for Inspection MICHAEL PELHAM
Deputy Reinf. Concrete 5/20/2021 No Access for Inspection VINCENT HANLEY
Deputy Reinf. Concrete 5/21/2021 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/2/2021 Corrections Issued STEVEN BACK
Deputy Reinf. Concrete 6/22/2021 Approved VINCENT HANLEY
ELECTRICAL-Rough 7/14/2021 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 7/14/2021 Approved VINCENT HANLEY
HVAC-Rough 7/14/2021 Approved VINCENT HANLEY
PLUMBING-Rough 7/14/2021 Approved VINCENT HANLEY
HVAC-Rough 8/4/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 8/16/2021 Approved VINCENT HANLEY
Green Building Rough 8/16/2021 Approved VINCENT HANLEY
Insulation 8/16/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 8/16/2021 Partial Approval VINCENT HANLEY
Shower Pan 8/16/2021 Approved VINCENT HANLEY
Wood Frame 8/16/2021 Approved VINCENT HANLEY
Drywall Nailing 9/3/2021 Approved RYAN SALAZAR
Interior/Exterior Lathing 9/3/2021 Approved RYAN SALAZAR
ELECTRICAL-Final 10/4/2021 Corrections Issued VINCENT HANLEY
Final 10/4/2021 Corrections Issued VINCENT HANLEY
Green Building Final 10/4/2021 Corrections Issued VINCENT HANLEY
HVAC-Final 10/4/2021 Corrections Issued VINCENT HANLEY
PLUMBING-Final 10/4/2021 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 10/4/2021 SGSOV Approved VINCENT HANLEY
Smoke Detectors 10/4/2021 Approved VINCENT HANLEY
ELECTRICAL-Final 10/14/2021 No Access for Inspection VINCENT HANLEY
Service/Power Release 10/14/2021 No Access for Inspection VINCENT HANLEY
ELECTRICAL-Final 10/19/2021 Corrections Issued DAVID SANDOVAL
PLUMBING-Final 10/19/2021 Not Ready for Inspection DAVID SANDOVAL
ELECTRICAL-Final 10/22/2021 Approved VINCENT HANLEY
Final 10/22/2021 Corrections Issued VINCENT HANLEY
Gas Test 10/22/2021 Approved VINCENT HANLEY
HVAC-Final 10/22/2021 Approved VINCENT HANLEY
PLUMBING-Final 10/22/2021 Approved VINCENT HANLEY
Final 12/6/2021 OK to Issue CofO VINCENT HANLEY
Green Building Final 12/6/2021 Approved VINCENT HANLEY