7237 N TUJUNGA AVE 91605
Certificate Information: 7237 N TUJUNGA AVE 91605
- Application / Permit
- 20014-20000-05734
- Plan Check / Job No.
- B20VN16531
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 19'-8" X 22'-4" IRREGULAR SHAPED ADDITION AND REMODEL (E) SFD. ADD 10' X 11' ATTACHED PATIO COVER. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/20/2021
- Issuing Office
- Current Status
- CofO Issued on 7/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/8/2021 | RAPHAEL ROSAS |
| Corrections Issued | 1/9/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 5/18/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 5/25/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 8/28/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 8/31/2021 | APPLICANT |
| Issued | 9/20/2021 | APPLICANT |
| CofO in Progress | 6/15/2022 | MATT KELLERMAN |
| CofO Issued | 7/21/2022 | RONALD MYRICK |
| Permit Finaled | 7/21/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2021 | GUILLERMO PETRA |
| Sewer availability | Cleared | 3/30/2021 | GUILLERMO PETRA |
| Low Impact Development | Cleared | 5/6/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 8/19/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/27/2021 | Approved | DANIEL DREW |
| Sewer | 9/29/2021 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 11/3/2021 | Approved | DANIEL DREW |
| Green Building Rough | 11/3/2021 | Approved | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2021 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 12/13/2021 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 12/23/2021 | Approved | JACK KARGODORIAN |
| Wood Frame | 12/23/2021 | Conditional Approval | JACK KARGODORIAN |
| Insulation | 12/29/2021 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 12/29/2021 | Partial Approval | JOHN KIDWELL |
| Shower Pan | 12/29/2021 | Approved | JOHN KIDWELL |
| Drywall Nailing | 1/4/2022 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 1/4/2022 | Partial Approval | CALEB MEISTER |
| ELECTRICAL-Final | 5/11/2022 | Corrections Issued | MISAEL ESPARZA |
| Final | 5/11/2022 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 5/11/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 5/11/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 5/11/2022 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 5/11/2022 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 5/11/2022 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 5/18/2022 | Corrections Issued | MATT KELLERMAN |
| Final | 5/18/2022 | Corrections Issued | MATT KELLERMAN |
| Green Building Final | 5/18/2022 | Approved | MATT KELLERMAN |
| HVAC-Final | 5/18/2022 | Approved | MATT KELLERMAN |
| PLUMBING-Final | 5/18/2022 | Corrections Issued | MATT KELLERMAN |
| Smoke Detectors | 5/18/2022 | Approved | MATT KELLERMAN |
| ELECTRICAL-Final | 6/2/2022 | Approved | MISAEL ESPARZA |
| Final | 6/2/2022 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Final | 6/2/2022 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 6/2/2022 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 6/14/2022 | Approved | MATT KELLERMAN |
| Final | 6/14/2022 | OK to Issue CofO | MATT KELLERMAN |
| HVAC-Final | 6/14/2022 | Approved | MATT KELLERMAN |
| PLUMBING-Final | 6/14/2022 | Approved | MATT KELLERMAN |