2800-2802 S MCCONNELL DR 90064

Certificate Information: 2800-2802 S MCCONNELL DR 90064

Application / Permit
20014-20000-05731
Plan Check / Job No.
B20VN16517
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL TO EXISTING SINGLE FAMILY DWELLING; CONVERT EXISTING ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 5/24/2021
Issuing Office
Current Status
CofO Issued on 7/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2020 APPLICANT
Assigned to Plan Check Engineer 12/30/2020 SELLA BENYAMIN
Corrections Issued 1/5/2021 SELLA BENYAMIN
Quality Review Completed 1/7/2021 STEVEN KIM
Building Plans Picked Up 1/8/2021 APPLICANT
Plan Check Approved 3/23/2021 SELLA BENYAMIN
Issued 5/24/2021 APPLICANT
CofO in Progress 7/13/2022 KENNETH NAGLE
Permit Finaled 7/13/2022 KENNETH NAGLE
CofO Issued 7/13/2022 KENNETH NAGLE
Permit Finaled 7/13/2022 KENNETH NAGLE

Permit Application Clearance Information

Address approval Cleared 1/7/2021 DINAH GARIN
Specific Plan Cleared 1/28/2021 PEDRO AYALA
Eng Process Fee Ord 176,300 Cleared 3/11/2021 DINAH GARIN
Roof/Waste drainage to street Cleared 3/11/2021 DINAH GARIN
Sewer availability Cleared 3/11/2021 DINAH GARIN

Contact Information

Contractor D Construction Group; Lic. No.: 1070841-B PO BOX 18429      BEVERLY HILLS, CA 90209
Engineer Mroczka,, Peter J; Lic. No.: C42648 9301 DARBY AVE APT 1      NORTHRIDGE, CA 91325

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/28/2021 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 6/2/2021 Not Ready for Inspection KEVIN SARGSYAN
Green Building Rough 6/2/2021 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Rough 6/2/2021 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 7/19/2021 Partial Approval KEVIN SARGSYAN
Special/Order Compliance 7/19/2021 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 8/11/2021 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 8/18/2021 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 8/18/2021 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 8/24/2021 Partial Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 10/8/2021 Not Ready for Inspection KEVIN SARGSYAN
Green Building Rough 10/8/2021 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Rough 10/8/2021 Not Ready for Inspection KEVIN SARGSYAN
Rough-Elec/Plmb/HVAC 10/8/2021 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 10/15/2021 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 10/15/2021 Approved KEVIN SARGSYAN
Green Building Rough 10/15/2021 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 10/15/2021 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Rough 10/15/2021 Approved KEVIN SARGSYAN
PLUMBING-Rough 10/15/2021 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 10/22/2021 Not Ready for Inspection KEVIN SARGSYAN
Rough-Elec/Plmb/HVAC 10/25/2021 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 10/28/2021 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 10/28/2021 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 11/1/2021 Partial Approval EVAN COOPER
Green Building Rough 11/1/2021 Approved EVAN COOPER
HVAC-Rough 11/1/2021 Approved EVAN COOPER
Interior/Exterior Lathing 11/1/2021 Partial Approval EVAN COOPER
Insulation 11/8/2021 Approved KEVIN SARGSYAN
Drywall Nailing 11/19/2021 Approved KEVIN SARGSYAN
Gas Test 11/29/2021 Partial Inspection KRISTEN CAUSEY
Sewer 11/29/2021 Approved KRISTEN CAUSEY
Shower Pan 11/29/2021 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 12/7/2021 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 5/26/2022 Approved KEVIN SARGSYAN
Final 5/26/2022 Corrections Issued KEVIN SARGSYAN
Green Building Final 5/26/2022 Corrections Issued KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 5/26/2022 SGSOV Not Ready KEVIN SARGSYAN
Smoke Detectors 5/26/2022 Approved KEVIN SARGSYAN
ELECTRICAL-Final 6/7/2022 Approved KENNETH NAGLE
Final 6/7/2022 Conditional Approval KENNETH NAGLE
Green Building Final 6/7/2022 Approved KENNETH NAGLE
HVAC-Final 6/7/2022 Approved KENNETH NAGLE
PLUMBING-Final 6/7/2022 Approved KENNETH NAGLE
SGSOV-Seismic Gas S/O Valve 6/7/2022 SGSOV Approved KENNETH NAGLE