8113 S NAYLOR AVE 90045
Certificate Information: 8113 S NAYLOR AVE 90045
- Application / Permit
- 20014-20000-05725
- Plan Check / Job No.
- B20VN16505
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 14'-9" X 45'-0" ACCESSORY DWELLING UNIT ADDITION TO (E) GARAGE PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 7/27/2021
- Issuing Office
- Current Status
- CofO Issued on 2/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2021 | ARTIN ZARUKIAN |
| Corrections Issued | 1/9/2021 | ARTIN ZARUKIAN |
| Plan Check Approved | 7/27/2021 | ARTIN ZARUKIAN |
| Issued | 7/27/2021 | APPLICANT |
| Building Plans Picked Up | 7/29/2021 | APPLICANT |
| CofO in Progress | 2/9/2023 | BOBBY KEY |
| Permit Finaled | 2/10/2023 | DANIEL ORRANTE |
| CofO Issued | 2/10/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/10/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Miscellaneous | Cleared | 1/20/2021 | LAUREN PADICK |
| Address approval | Cleared | 2/4/2021 | NIKTA MOUSAVI |
| Eng Process Fee Ord 176,300 | Cleared | 2/5/2021 | NIKTA MOUSAVI |
| Sewer availability | Cleared | 2/5/2021 | NIKTA MOUSAVI |
| Low Impact Development | Cleared | 7/1/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 7/8/2021 | TRACY TATE |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | South Land Remodeling Inc; Lic. No.: 901842-B | 10770 DES MOINES AVE NORTHRIDGE, CA 91326 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/3/2021 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Underground Mechanical | 9/9/2021 | Corrections Issued | BRENDAN LOONEY |
| Underground Mechanical | 9/13/2021 | Approved | WILLIAM MICHALAK |
| Deputy Drilled-In Anchors | 9/15/2021 | Conditional Approval | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 9/16/2021 | Approved | JUAN VALENZUELA |
| Footing/Foundation/Slab | 9/16/2021 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 9/27/2021 | Corrections Issued | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2021 | Conditional Approval | BRENDAN LOONEY |
| Green Building Rough | 9/27/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| ELECTRICAL-Rough | 10/12/2021 | Partial Approval | DEANDRE HOFFMAN |
| HVAC-Rough | 10/12/2021 | Corrections Issued | DEANDRE HOFFMAN |
| PLUMBING-Rough | 10/12/2021 | Approved | DEANDRE HOFFMAN |
| Wood Frame | 10/18/2021 | Not Ready for Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2021 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Rough | 3/2/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 3/2/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 3/16/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Shower Pan | 3/16/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 3/23/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 4/4/2022 | Approved | BOBBY KEY |
| Green Building Rough | 4/4/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 4/4/2022 | Approved | BOBBY KEY |
| Insulation | 5/3/2022 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 5/12/2022 | Approved | BOBBY KEY |
| Final | 5/12/2022 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 5/12/2022 | Approved | BOBBY KEY |
| Shower Pan | 5/12/2022 | Approved | BOBBY KEY |
| HVAC-Final | 6/28/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 6/28/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Underground Mechanical | 6/28/2022 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 8/11/2022 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 8/11/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 10/20/2022 | Corrections Issued | BOBBY KEY |
| Final | 10/20/2022 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Final | 10/20/2022 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 10/20/2022 | SGSOV Approved | BOBBY KEY |
| ELECTRICAL-Final | 10/24/2022 | Conditional Approval | BOBBY KEY |
| HVAC-Final | 10/24/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 10/24/2022 | Conditional Approval | BOBBY KEY |
| Service/Power Release | 10/24/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 2/9/2023 | Approved | BOBBY KEY |
| Final | 2/9/2023 | OK to Issue CofO | BOBBY KEY |
| Gas Test | 2/9/2023 | Approved | BOBBY KEY |
| Green Building Final | 2/9/2023 | Approved | BOBBY KEY |
| HVAC-Final | 2/9/2023 | Approved | BOBBY KEY |
| PLUMBING-Final | 2/9/2023 | Approved | BOBBY KEY |
| Smoke Detectors | 2/9/2023 | Approved | BOBBY KEY |