19516 W ENADIA WAY 91335

Certificate Information: 19516 W ENADIA WAY 91335

Application / Permit
20014-20000-05697
Plan Check / Job No.
B20VN16440
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 5'-4.5" X 9'-1" ADDITION FOR (N) BATHROOM TO (E) SFD. ALL WORK PER WFPP.
Permit Issued
Issued on 1/27/2021
Issuing Office
Current Status
CofO Issued on 4/12/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/22/2020 APPLICANT
Assigned to Plan Check Engineer 12/30/2020 RAPHAEL ROSAS
Corrections Issued 1/1/2021 RAPHAEL ROSAS
Applicant returned to address corrections 1/15/2021 RAPHAEL ROSAS
Plan Check Approved 1/17/2021 RAPHAEL ROSAS
Issued 1/27/2021 APPLICANT
CofO in Progress 3/16/2021 VINCENT HANLEY
Permit Finaled 4/12/2021 MICHAEL SMITH
CofO Issued 4/12/2021 MICHAEL SMITH
Permit Finaled 4/12/2021 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/5/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 1/6/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/2/2021 Approved VINCENT HANLEY
PLUMBING-Rough 2/4/2021 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 2/8/2021 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 2/19/2021 Approved VINCENT HANLEY
ELECTRICAL-Rough 2/19/2021 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 2/19/2021 Approved VINCENT HANLEY
Green Building Rough 2/19/2021 Approved VINCENT HANLEY
PLUMBING-Rough 2/19/2021 Approved VINCENT HANLEY
Insulation 2/25/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 2/25/2021 Approved VINCENT HANLEY
Shower Pan 2/25/2021 Approved VINCENT HANLEY
Drywall Nailing 2/26/2021 Approved VINCENT HANLEY
Final 3/11/2021 Corrections Issued VINCENT HANLEY
Green Building Final 3/11/2021 Approved VINCENT HANLEY
Smoke Detectors 3/11/2021 Approved VINCENT HANLEY
ELECTRICAL-Final 3/16/2021 Approved VINCENT HANLEY
Final 3/16/2021 OK to Issue CofO VINCENT HANLEY
HVAC-Final 3/16/2021 Approved VINCENT HANLEY
PLUMBING-Final 3/16/2021 Approved VINCENT HANLEY