11227 N HASKELL AVE 91344

Certificate Information: 11227 N HASKELL AVE 91344

Application / Permit
20014-20000-05680
Plan Check / Job No.
B20VN16383
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 22' 11" X 29' 2-STORY ACCESSORY DWELLING TO (E) DETACHED 2-CAR GARAGE PER LAMC 12.22 A.33(c) AND (d). ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 7/27/2021
Issuing Office
Current Status
CofO Issued on 9/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/21/2020 APPLICANT
Assigned to Plan Check Engineer 1/14/2021 GURUNATH NESARAJAH
Corrections Issued 1/16/2021 GURUNATH NESARAJAH
Quality Review Completed 2/4/2021 OMID HEDAYAT
Building Plans Picked Up 2/4/2021 APPLICANT
Plan Check Approved 7/21/2021 GURUNATH NESARAJAH
Issued 7/27/2021 APPLICANT
CofO in Progress 9/13/2023 ROBERT GOLD
Permit Finaled 9/25/2023 RUBEN SALAS
CofO Issued 9/25/2023 RUBEN SALAS
Permit Finaled 9/25/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/5/2021 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 2/8/2021 LEE GUILBEAUX
Sewer availability Cleared 2/8/2021 LEE GUILBEAUX
Grading Pre-Inspection Cleared 5/18/2021 BRIAN MILLER
Low Impact Development Cleared 7/8/2021 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 7/9/2021 DAGOVERTO GUERRERO
GPI Written Notices Cleared 7/21/2021 GURUNATH NESARAJAH

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/14/2021 Partial Inspection JENNIFER RABUCHIN
PLUMBING-Rough 12/21/2021 Corrections Issued MICHAEL TEMPLE
PLUMBING-Rough 1/6/2022 Partial Approval JENNIFER RABUCHIN
Deputy Drilled-In Anchors 1/7/2022 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 1/10/2022 Corrections Issued MARK JOHNSON
Footing/Foundation/Slab 1/19/2022 Approved JENNIFER RABUCHIN
Wood Frame 2/8/2022 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 3/9/2022 Corrections Issued RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 3/14/2022 Partial Approval JENNIFER RABUCHIN
HVAC-Rough 4/11/2022 Approved MICHAEL TEMPLE
ELECTRICAL-Rough 4/15/2022 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 4/15/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 4/27/2022 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 4/27/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 4/27/2022 Not Ready for Inspection JENNIFER RABUCHIN
Wood Frame 4/27/2022 Partial Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/13/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 5/13/2022 Approved JENNIFER RABUCHIN
Green Building Rough 5/13/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 5/13/2022 Partial Approval JENNIFER RABUCHIN
Underground Mechanical 5/13/2022 Approved JENNIFER RABUCHIN
Insulation 5/23/2022 Approved JENNIFER RABUCHIN
Shower Pan 5/23/2022 Approved JENNIFER RABUCHIN
Drywall Nailing 6/3/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 8/17/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 2/8/2023 Corrections Issued JENNIFER RABUCHIN
Final 2/8/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Final 2/8/2023 Approved JENNIFER RABUCHIN
HVAC-Final 2/8/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 2/8/2023 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 2/8/2023 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 2/8/2023 Approved JENNIFER RABUCHIN
Final 7/6/2023 Corrections Issued JENNIFER RABUCHIN
Final 8/17/2023 Partial Inspection ROBERT GOLD
Final 9/8/2023 Corrections Issued JENNIFER RABUCHIN
Final 9/13/2023 OK to Issue CofO ROBERT GOLD