4316 S HOBART BLVD 90062

Certificate Information: 4316 S HOBART BLVD 90062

Application / Permit
20014-20000-05676
Plan Check / Job No.
B20VN16368
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
32'-6" X 16' IRREG SHAPED ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d). ALL WORK PER ENGR.
Permit Issued
Issued on 8/8/2022
Issuing Office
Valley
Current Status
CofO Issued on 1/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/11/2021 APPLICANT
Assigned to Plan Check Engineer 1/22/2021 HAYATO TSUCHIYA
Corrections Issued 1/24/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 3/4/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 5/7/2021 GURUNATH NESARAJAH
Applicant returned to address corrections 4/21/2022 HAYATO TSUCHIYA
Applicant returned to address corrections 7/6/2022 HAYATO TSUCHIYA
Applicant returned to address corrections 7/18/2022 HAYATO TSUCHIYA
Plan Check Approved 8/1/2022 JEROME MAGAT PALMA
Building Plans Picked Up 8/1/2022 APPLICANT
Issued 8/8/2022 APPLICANT
CofO in Progress 1/21/2025 SABAS ALONSO
Permit Finaled 1/26/2025 DEROLD HAUFF
CofO Issued 1/26/2025 DEROLD HAUFF
Permit Finaled 1/26/2025 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 6/2/2021 RIDWAN HARDY
Address approval Cleared 11/9/2021 CINDY QI
Permit Cleared 11/9/2021 CINDY QI
Eng Process Fee Ord 176,300 Cleared 12/20/2021 CINDY QI
Sewer availability Cleared 12/20/2021 CINDY QI
Low Impact Development Cleared 1/25/2022 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 2/14/2022 CINDY QI

Contact Information

Engineer Kator,, Khaled; Lic. No.: C69781 19519 TULSA ST      NORTHRIDGE, CA 91326

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 11/21/2022 Approved SABAS ALONSO
Underground Mechanical 11/21/2022 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 12/1/2022 Not Ready for Inspection SABAS ALONSO
Footing/Foundation/Slab 12/6/2022 Corrections Issued HORACE FULTZ
Footing/Foundation/Slab 1/18/2023 Not Ready for Inspection SABAS ALONSO
Excavation/Setback/Form/Re-Bar 3/17/2023 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 3/17/2023 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 5/23/2023 Approved SABAS ALONSO
BUILDING-Rough-Frame 10/11/2023 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 10/11/2023 Corrections Issued SABAS ALONSO
Green Building Rough 10/11/2023 Corrections Issued SABAS ALONSO
HVAC-Rough 10/11/2023 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 10/11/2023 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 11/8/2023 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 11/8/2023 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 11/8/2023 Corrections Issued SABAS ALONSO
Green Building Rough 11/8/2023 Approved SABAS ALONSO
HVAC-Rough 11/8/2023 Corrections Issued SABAS ALONSO
PLUMBING-Rough 11/8/2023 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 11/29/2023 Corrections Issued SABAS ALONSO
HVAC-Rough 11/29/2023 Corrections Issued SABAS ALONSO
Deputy Wood Construction 12/20/2023 Conditional Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/21/2023 Corrections Issued SABAS ALONSO
HVAC-Rough 12/21/2023 Approved SABAS ALONSO
BUILDING-Rough-Frame 1/8/2024 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 1/8/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 1/8/2024 Partial Approval SABAS ALONSO
Insulation 1/16/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 1/16/2024 Partial Approval SABAS ALONSO
Shower Pan 1/16/2024 Partial Approval SABAS ALONSO
Drywall Nailing 2/14/2024 Not Ready for Inspection SABAS ALONSO
Shower Pan 2/14/2024 Not Ready for Inspection SABAS ALONSO
Drywall Nailing 2/29/2024 Approved BRENDAN MORELLI
Shower Pan 2/29/2024 Approved BRENDAN MORELLI
Final 6/25/2024 Corrections Issued SABAS ALONSO
Green Building Final 6/25/2024 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 6/25/2024 SGSOV Approved SABAS ALONSO
Smoke Detectors 6/25/2024 Approved SABAS ALONSO
Final 12/12/2024 Corrections Issued SABAS ALONSO
Green Building Final 12/12/2024 Approved SABAS ALONSO
Final 1/14/2025 OK to Issue CofO SABAS ALONSO