5018 N GREENBUSH AVE 91423

Certificate Information: 5018 N GREENBUSH AVE 91423

Application / Permit
20014-20000-05668
Plan Check / Job No.
B20VN16350
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL; REMOVE 36'-11" X 38'-1" SINGLE FAMILY DWELLING EXCEPT FOR 6' OF WALL AND FOOTING ON EAST SIDE; ADD 43'-5" X 80'-6" SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 5/26/2021
Issuing Office
Current Status
CofO Issued on 4/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/18/2020 APPLICANT
Assigned to Plan Check Engineer 12/23/2020 SELLA BENYAMIN
Corrections Issued 12/28/2020 SELLA BENYAMIN
Quality Review Completed 12/30/2020 STEVEN KIM
Building Plans Picked Up 1/8/2021 APPLICANT
Plan Check Approved 5/26/2021 SELLA BENYAMIN
Issued 5/26/2021 APPLICANT
CofO in Progress 3/16/2022 MISAEL ESPARZA
Permit Finaled 4/11/2022 MICHAEL SMITH
CofO Issued 4/11/2022 MICHAEL SMITH
Permit Finaled 4/11/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/28/2021 JOHN TRIANTAFYLLOS
Permit Cleared 1/28/2021 JOHN TRIANTAFYLLOS
Trees in Parkway Cleared 2/4/2021 JOHN KIM
Hydrant and Access approval Cleared 3/11/2021 JOHN CONNEALLY
Sewer availability Cleared 4/28/2021 JOHN TRIANTAFYLLOS
Low Impact Development Cleared 5/16/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 5/18/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/6/2021 Approved CHARLES POWELL
Footing/Foundation/Slab 7/15/2021 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 8/24/2021 Partial Approval CHARLES POWELL
HVAC-Rough 8/24/2021 Approved CHARLES POWELL
ELECTRICAL-Rough 9/1/2021 Approved CHARLES POWELL
PLUMBING-Rough 9/1/2021 Approved CHARLES POWELL
BUILDING-Rough-Frame 9/27/2021 Corrections Issued ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 9/27/2021 Approved ALIZAH MAYAGOITIA
Green Building Rough 9/27/2021 Not Ready for Inspection ALIZAH MAYAGOITIA
Special/Order Compliance 9/27/2021 Partial Inspection ARAM AVEDISIAN
Verify Sprinkler Sign Off 9/27/2021 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 9/29/2021 Approved ALIZAH MAYAGOITIA
Green Building Rough 9/29/2021 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 9/29/2021 Partial Approval ALIZAH MAYAGOITIA
Insulation 10/5/2021 Conditional Approval MISAEL ESPARZA
Shower Pan 10/5/2021 Approved MISAEL ESPARZA
Drywall Nailing 10/14/2021 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 10/14/2021 Partial Approval ASHLEY THOMPSON
Interior/Exterior Lathing 10/18/2021 Approved ASHLEY THOMPSON
Gas Test 2/11/2022 Approved MISAEL ESPARZA
HVAC-Final 2/11/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 2/11/2022 Corrections Issued MISAEL ESPARZA
HVAC-Final 2/23/2022 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Final 2/23/2022 Approved MISAEL ESPARZA
ELECTRICAL-Final 3/7/2022 Corrections Issued MISAEL ESPARZA
HVAC-Final 3/7/2022 Approved MISAEL ESPARZA
ELECTRICAL-Final 3/11/2022 Approved MISAEL ESPARZA
Final 3/15/2022 OK to Issue CofO MISAEL ESPARZA
Green Building Final 3/15/2022 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 3/15/2022 SGSOV Approved MISAEL ESPARZA
Service/Power Release 3/15/2022 Approved MISAEL ESPARZA
Smoke Detectors 3/15/2022 Approved MISAEL ESPARZA