7700 N SEDAN AVE 91304
Certificate Information: 7700 N SEDAN AVE 91304
- Application / Permit
- 20014-20000-05666
- Plan Check / Job No.
- B20VN16348
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 30' 5" X 5' 6" SIDE ADDITION, 24' X 9' 11" FRONT ADDITION, 6' 5" X 3' FRONT PORCH ADDITION AND MAJOR INTERIOR REMODEL TO (E) SFD. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 4/3/2021
- Issuing Office
- Current Status
- CofO Issued on 7/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 1/2/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 3/31/2021 | GURUNATH NESARAJAH |
| Issued | 4/3/2021 | APPLICANT |
| Building Plans Picked Up | 4/5/2021 | APPLICANT |
| CofO in Progress | 7/13/2022 | CHRIS CHRISTENSEN |
| Permit Finaled | 7/26/2022 | JOHN JANSON |
| CofO Issued | 7/26/2022 | JOHN JANSON |
| Permit Finaled | 7/26/2022 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 1/6/2021 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 3/16/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 3/18/2021 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 8916 LONGDON AVE #C TEMPLE CITY, CA 91780 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/19/2021 | Corrections Issued | DAVID STEPANYAN |
| Footing/Foundation/Slab | 4/19/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| PLUMBING-Rough | 4/19/2021 | Corrections Issued | DAVID STEPANYAN |
| Footing/Foundation/Slab | 4/27/2021 | Partial Approval | DAVID STEPANYAN |
| PLUMBING-Rough | 4/27/2021 | Partial Approval | DAVID STEPANYAN |
| Footing/Foundation/Slab | 5/10/2021 | Approved | DAVID STEPANYAN |
| PLUMBING-Rough | 5/10/2021 | Partial Approval | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 5/24/2021 | Corrections Issued | DAVID STEPANYAN |
| ELECTRICAL-Rough | 5/24/2021 | Corrections Issued | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2021 | Partial Approval | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 6/15/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| ELECTRICAL-Rough | 6/15/2021 | Approved | DAVID STEPANYAN |
| Green Building Rough | 6/15/2021 | Corrections Issued | DAVID STEPANYAN |
| HVAC-Rough | 6/15/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| PLUMBING-Rough | 6/15/2021 | Corrections Issued | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 6/21/2021 | Partial Approval | DAVID STEPANYAN |
| Green Building Rough | 6/21/2021 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 6/21/2021 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 6/21/2021 | Partial Approval | DAVID STEPANYAN |
| PLUMBING-Rough | 6/21/2021 | Approved | DAVID STEPANYAN |
| Insulation | 6/25/2021 | Approved | SHAVONNE ESPINOZA |
| Shower Pan | 6/25/2021 | Partial Approval | SHAVONNE ESPINOZA |
| Drywall Nailing | 7/6/2021 | Corrections Issued | SHAVONNE ESPINOZA |
| Interior/Exterior Lathing | 7/6/2021 | Approved | SHAVONNE ESPINOZA |
| Drywall Nailing | 7/23/2021 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 8/20/2021 | Corrections Issued | DAVID STEPANYAN |
| Gas Test | 8/20/2021 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 9/9/2021 | Approved | DAVID STEPANYAN |
| Footing/Foundation/Slab | 9/9/2021 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Final | 6/10/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 6/10/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 6/10/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Final | 6/10/2022 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 6/10/2022 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 6/10/2022 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 6/10/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 7/6/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 7/6/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Final | 7/13/2022 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 7/13/2022 | Approved | CHRIS CHRISTENSEN |