7700 N SEDAN AVE 91304

Certificate Information: 7700 N SEDAN AVE 91304

Application / Permit
20014-20000-05666
Plan Check / Job No.
B20VN16348
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
30' 5" X 5' 6" SIDE ADDITION, 24' X 9' 11" FRONT ADDITION, 6' 5" X 3' FRONT PORCH ADDITION AND MAJOR INTERIOR REMODEL TO (E) SFD. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 4/3/2021
Issuing Office
Current Status
CofO Issued on 7/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/18/2020 APPLICANT
Assigned to Plan Check Engineer 12/30/2020 GURUNATH NESARAJAH
Corrections Issued 1/2/2021 GURUNATH NESARAJAH
Plan Check Approved 3/31/2021 GURUNATH NESARAJAH
Issued 4/3/2021 APPLICANT
Building Plans Picked Up 4/5/2021 APPLICANT
CofO in Progress 7/13/2022 CHRIS CHRISTENSEN
Permit Finaled 7/26/2022 JOHN JANSON
CofO Issued 7/26/2022 JOHN JANSON
Permit Finaled 7/26/2022 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/6/2021 ADRIAN CASTRO
Sewer availability Cleared 1/6/2021 ADRIAN CASTRO
Low Impact Development Cleared 3/16/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 3/18/2021 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/19/2021 Corrections Issued DAVID STEPANYAN
Footing/Foundation/Slab 4/19/2021 Not Ready for Inspection DAVID STEPANYAN
PLUMBING-Rough 4/19/2021 Corrections Issued DAVID STEPANYAN
Footing/Foundation/Slab 4/27/2021 Partial Approval DAVID STEPANYAN
PLUMBING-Rough 4/27/2021 Partial Approval DAVID STEPANYAN
Footing/Foundation/Slab 5/10/2021 Approved DAVID STEPANYAN
PLUMBING-Rough 5/10/2021 Partial Approval DAVID STEPANYAN
BUILDING-Rough-Frame 5/24/2021 Corrections Issued DAVID STEPANYAN
ELECTRICAL-Rough 5/24/2021 Corrections Issued DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 5/24/2021 Partial Approval DAVID STEPANYAN
BUILDING-Rough-Frame 6/15/2021 Not Ready for Inspection DAVID STEPANYAN
ELECTRICAL-Rough 6/15/2021 Approved DAVID STEPANYAN
Green Building Rough 6/15/2021 Corrections Issued DAVID STEPANYAN
HVAC-Rough 6/15/2021 Not Ready for Inspection DAVID STEPANYAN
PLUMBING-Rough 6/15/2021 Corrections Issued DAVID STEPANYAN
BUILDING-Rough-Frame 6/21/2021 Partial Approval DAVID STEPANYAN
Green Building Rough 6/21/2021 Approved DAVID STEPANYAN
HVAC-Rough 6/21/2021 Approved DAVID STEPANYAN
Interior/Exterior Lathing 6/21/2021 Partial Approval DAVID STEPANYAN
PLUMBING-Rough 6/21/2021 Approved DAVID STEPANYAN
Insulation 6/25/2021 Approved SHAVONNE ESPINOZA
Shower Pan 6/25/2021 Partial Approval SHAVONNE ESPINOZA
Drywall Nailing 7/6/2021 Corrections Issued SHAVONNE ESPINOZA
Interior/Exterior Lathing 7/6/2021 Approved SHAVONNE ESPINOZA
Drywall Nailing 7/23/2021 Approved RYAN SALAZAR
BUILDING-Rough-Frame 8/20/2021 Corrections Issued DAVID STEPANYAN
Gas Test 8/20/2021 Approved DAVID STEPANYAN
BUILDING-Rough-Frame 9/9/2021 Approved DAVID STEPANYAN
Footing/Foundation/Slab 9/9/2021 Approved DAVID STEPANYAN
ELECTRICAL-Final 6/10/2022 Approved CHRIS CHRISTENSEN
Final 6/10/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 6/10/2022 Corrections Issued CHRIS CHRISTENSEN
HVAC-Final 6/10/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Final 6/10/2022 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 6/10/2022 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 6/10/2022 Approved CHRIS CHRISTENSEN
Final 7/6/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Final 7/6/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Final 7/13/2022 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 7/13/2022 Approved CHRIS CHRISTENSEN