23630 W KIRUNA PL 91367
Certificate Information: 23630 W KIRUNA PL 91367
- Application / Permit
- 20014-20000-05662
- Plan Check / Job No.
- B20VN16337
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT 29' 10" X 19' 7" IRR.-SHAPE GARAGE TO HABITABLE SPACE AND ADD 19' 7" X 20' 6" 2-CAR GARAGE TO FRONT OF (E) SFD. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 3/8/2021
- Issuing Office
- Current Status
- CofO Issued on 8/10/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 1/2/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 2/26/2021 | GURUNATH NESARAJAH |
| Issued | 3/8/2021 | APPLICANT |
| Building Plans Picked Up | 3/12/2021 | APPLICANT |
| CofO in Progress | 8/8/2021 | TROY SANDERS |
| Permit Finaled | 8/10/2021 | JOHN JANSON |
| CofO Issued | 8/10/2021 | JOHN JANSON |
| Permit Finaled | 8/10/2021 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2021 | GUILLERMO PETRA |
| Grading Pre-Inspection | Cleared | 1/21/2021 | BRIAN MILLER |
| Roof/Waste drainage to street | Cleared | 2/18/2021 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 3/10/2021 | Corrections Issued | TROY SANDERS |
| PLUMBING-Rough | 3/10/2021 | Corrections Issued | TROY SANDERS |
| Deputy Drilled-In Anchors | 3/26/2021 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 3/30/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 3/30/2021 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 3/30/2021 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 4/6/2021 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 4/20/2021 | Corrections Issued | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 4/20/2021 | Corrections Issued | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 4/28/2021 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 4/28/2021 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2021 | Approved | TROY SANDERS |
| Green Building Rough | 4/28/2021 | Approved | TROY SANDERS |
| Insulation | 4/28/2021 | Approved | TROY SANDERS |
| PLUMBING-Rough | 4/28/2021 | Approved | TROY SANDERS |
| Drywall Nailing | 5/4/2021 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 7/12/2021 | Approved | TROY SANDERS |
| Final | 7/12/2021 | Corrections Issued | TROY SANDERS |
| Footing/Foundation/Slab | 7/12/2021 | Approved | TROY SANDERS |
| Green Building Final | 7/12/2021 | Corrections Issued | TROY SANDERS |
| HVAC-Final | 7/12/2021 | Approved | TROY SANDERS |
| PLUMBING-Final | 7/12/2021 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 7/12/2021 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 7/12/2021 | Approved | TROY SANDERS |
| Final | 8/5/2021 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 8/5/2021 | Approved | TROY SANDERS |