8047 N ST CLAIR AVE 91605
Certificate Information: 8047 N ST CLAIR AVE 91605
- Application / Permit
- 20014-20000-05641
- Plan Check / Job No.
- B20VN16295
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 2-STORY 26'x27'-2" ACCESSORY DWELLING UNIT TO EXISTING GARAGE
- Permit Issued
- Issued on 5/7/2021
- Issuing Office
- Current Status
- Issued on 5/7/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2021 | ALYSSA N NARCISO |
| Corrections Issued | 1/22/2021 | ALYSSA N NARCISO |
| Quality Review Completed | 1/27/2021 | STEVEN KIM |
| Building Plans Picked Up | 1/28/2021 | APPLICANT |
| Applicant returned to address corrections | 5/4/2021 | ALYSSA N NARCISO |
| Plan Check Approved | 5/7/2021 | ALYSSA N NARCISO |
| Issued | 5/7/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/20/2021 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 2/5/2021 | GUILLERMO PETRA |
| Sewer availability | Cleared | 2/5/2021 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 3/5/2021 | KURT CORRAL |
| Construction near power lines | Cleared | 3/26/2021 | WALTER RAMIREZ |
| Construction within easement | Cleared | 3/26/2021 | WALTER RAMIREZ |
| Low Impact Development | Cleared | 4/23/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 4/27/2021 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/16/2022 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 8/7/2024 | No Access for Inspection | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 9/2/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Pre-Inspection | 4/7/2026 | Corrections Issued | MATTHEW NELSON |