19440 W COHASSET ST 91335

Certificate Information: 19440 W COHASSET ST 91335

Application / Permit
20014-20000-05640
Plan Check / Job No.
B20VN16289
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 31' X 22'-6" ATTACHED ADU WITH 9'-6" X 4'-0" ATTACHED PORCH TO (E) GARAGE PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 5/25/2021
Issuing Office
Current Status
CofO Issued on 9/21/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/21/2020 APPLICANT
Assigned to Plan Check Engineer 12/31/2020 PARISA ZAHABI
Corrections Issued 1/3/2021 PARISA ZAHABI
Applicant returned to address corrections 3/3/2021 PARISA ZAHABI
Plan Check Approved 5/24/2021 PINANK PATEL
Issued 5/25/2021 APPLICANT
Building Plans Picked Up 5/27/2021 APPLICANT
CofO in Progress 9/13/2021 VINCENT HANLEY
CofO Issued 9/21/2021 MICHAEL SMITH
Permit Finaled 9/21/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/21/2021 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 1/21/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/22/2021 ADRIAN CASTRO
Sewer availability Cleared 1/22/2021 ADRIAN CASTRO
Hydrant and Access approval Cleared 2/10/2021 MATTHEW CRAIG
Low Impact Development Cleared 5/16/2021 MARTIN FRAGOSO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/1/2021 Approved VINCENT HANLEY
PLUMBING-Rough 6/1/2021 Partial Approval VINCENT HANLEY
Sewer 6/1/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 6/9/2021 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 6/9/2021 Approved VINCENT HANLEY
Green Building Rough 6/9/2021 Not Ready for Inspection VINCENT HANLEY
Rough-Elec/Plmb/HVAC 6/9/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 6/17/2021 Approved VINCENT HANLEY
Green Building Rough 6/17/2021 Approved VINCENT HANLEY
Insulation 6/17/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 6/17/2021 Approved VINCENT HANLEY
Shower Pan 6/17/2021 Approved VINCENT HANLEY
Drywall Nailing 6/25/2021 Approved VINCENT HANLEY
Final 6/25/2021 Not Ready for Inspection VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 6/25/2021 SGSOV Not Ready VINCENT HANLEY
Smoke Detectors 6/25/2021 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Final 7/2/2021 Corrections Issued VINCENT HANLEY
Final 7/2/2021 Corrections Issued VINCENT HANLEY
Gas Test 7/2/2021 Approved VINCENT HANLEY
Green Building Final 7/2/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 7/2/2021 SGSOV Gas Company VINCENT HANLEY
Smoke Detectors 7/2/2021 Approved VINCENT HANLEY
ELECTRICAL-Final 9/10/2021 Approved VINCENT HANLEY
Final 9/10/2021 OK to Issue CofO VINCENT HANLEY
Gas Test 9/10/2021 Approved VINCENT HANLEY
HVAC-Final 9/10/2021 Approved VINCENT HANLEY
PLUMBING-Final 9/10/2021 Approved VINCENT HANLEY