12307 N LOUISE AVE 91344

Certificate Information: 12307 N LOUISE AVE 91344

Application / Permit
20014-20000-05639
Plan Check / Job No.
B20VN16287
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 11' X 14' IRREGULAR SHAPED ADDITION TO (E) SFD FOR (N) BEDROOM. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 2/26/2021
Issuing Office
Current Status
CofO Issued on 6/25/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/17/2020 APPLICANT
Assigned to Plan Check Engineer 12/23/2020 RAPHAEL ROSAS
Corrections Issued 12/25/2020 RAPHAEL ROSAS
Applicant returned to address corrections 2/8/2021 RAPHAEL ROSAS
Issued 2/26/2021 APPLICANT
Building Plans Picked Up 3/2/2021 APPLICANT
CofO in Progress 4/19/2021 DAVID SCANTLIN
Permit Finaled 6/25/2021 JOHN JANSON
CofO Issued 6/25/2021 JOHN JANSON
Permit Finaled 6/25/2021 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/13/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 1/13/2021 GABRIEL ROBLES
Sewer availability Cleared 1/13/2021 GABRIEL ROBLES
Grading Pre-Inspection Cleared 1/21/2021 MANUEL TEJADA

Contact Information

Contractor Owner-Builder       ,
Engineer Zelada,, Mynor Anibal; Lic. No.: C48666 14545 VICTORY BLVD 405      VAN NUYS, CA 91411

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/8/2021 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 3/22/2021 Approved DAVID SCANTLIN
ELECTRICAL-Rough 3/30/2021 Approved DAVID SCANTLIN
Insulation 3/30/2021 Approved DAVID SCANTLIN
Interior/Exterior Lathing 3/30/2021 Approved DAVID SCANTLIN
Drywall Nailing 4/12/2021 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 4/13/2021 Approved DAVID SCANTLIN
Final 4/13/2021 Corrections Issued DAVID SCANTLIN
Footing/Foundation/Slab 4/13/2021 Approved DAVID SCANTLIN
Green Building Final 4/13/2021 Approved DAVID SCANTLIN
Green Building Rough 4/13/2021 Approved DAVID SCANTLIN
METHANE-Barrier 4/13/2021 Approved DAVID SCANTLIN
METHANE-Final 4/13/2021 Approved DAVID SCANTLIN
METHANE-Rough 4/13/2021 Approved DAVID SCANTLIN
METHANE-Subgrade 4/13/2021 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 4/13/2021 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 4/13/2021 Approved DAVID SCANTLIN
Final 4/16/2021 OK to Issue CofO DAVID SCANTLIN