4930 N HESPERIA AVE 91316

Certificate Information: 4930 N HESPERIA AVE 91316

Application / Permit
20014-20000-05617
Plan Check / Job No.
B20VN16236
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER ORD #186,481.
Permit Issued
Issued on 3/26/2021
Issuing Office
Current Status
CofO Issued on 9/21/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/16/2020 APPLICANT
Assigned to Plan Check Engineer 12/30/2020 HAYATO TSUCHIYA
Corrections Issued 1/3/2021 HAYATO TSUCHIYA
Plan Check Approved 2/16/2021 HAYATO TSUCHIYA
Issued 3/26/2021 APPLICANT
CofO in Progress 9/15/2021 DAVID SANDOVAL
CofO Issued 9/21/2021 MICHAEL SMITH
Permit Finaled 9/21/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/13/2021 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 1/13/2021 GUILLERMO PETRA
Sewer availability Cleared 1/13/2021 GUILLERMO PETRA
Grading Pre-Inspection Cleared 1/26/2021 BRIAN MILLER
Eng Process Fee Ord 176,300 Cleared 2/10/2021 GUILLERMO PETRA

Contact Information

Architect , ; Lic. No.: C35092       ,
Contractor Ind Construction Llc; Lic. No.: 937833-B 16430 VENTURA BLVD STE 208      ENCINO, CA 91436
Engineer Aronianpour,, Eilan; Lic. No.: C88101 7242 JELLICO AVE      LAKE BALBOA, CA 91406

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/7/2021 Corrections Issued DAVID SANDOVAL
Sewer 4/7/2021 Approved DAVID SANDOVAL
Footing/Foundation/Slab 4/13/2021 Approved DAVID SANDOVAL
Underground Mechanical 4/13/2021 Partial Approval DAVID SANDOVAL
Underground Mechanical 5/5/2021 Partial Approval DAVID SANDOVAL
ELECTRICAL-Rough 5/12/2021 Not Ready for Inspection RONALD COWAN
HVAC-Rough 5/12/2021 Not Ready for Inspection RONALD COWAN
PLUMBING-Rough 5/12/2021 Not Ready for Inspection RONALD COWAN
Wood Frame 5/12/2021 Not Ready for Inspection RONALD COWAN
ELECTRICAL-Rough 5/19/2021 Not Ready for Inspection RONALD COWAN
HVAC-Rough 5/19/2021 Approved RONALD COWAN
PLUMBING-Rough 5/19/2021 Approved RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 5/25/2021 Not Ready for Inspection DAVID SANDOVAL
Insulation 5/25/2021 Partial Approval DAVID SANDOVAL
ELECTRICAL-Rough 6/4/2021 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 6/4/2021 Approved DAVID SANDOVAL
PLUMBING-Rough 6/4/2021 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 6/15/2021 Approved DAVID SANDOVAL
Green Building Rough 6/15/2021 Approved DAVID SANDOVAL
Insulation 6/15/2021 Approved DAVID SANDOVAL
Interior/Exterior Lathing 6/15/2021 Approved DAVID SANDOVAL
Drywall Nailing 6/28/2021 Approved STEPHANIE SWANSON
ELECTRICAL-Final 8/13/2021 Not Ready for Inspection DAVID SANDOVAL
Final 8/13/2021 Corrections Issued DAVID SANDOVAL
Green Building Final 8/13/2021 Not Ready for Inspection DAVID SANDOVAL
HVAC-Final 8/13/2021 Approved DAVID SANDOVAL
PLUMBING-Final 8/13/2021 Not Ready for Inspection DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 8/13/2021 SGSOV Not Ready DAVID SANDOVAL
Smoke Detectors 8/13/2021 Approved DAVID SANDOVAL
ELECTRICAL-Final 8/26/2021 Approved DAVID SANDOVAL
Final 8/26/2021 Corrections Issued DAVID SANDOVAL
Green Building Final 8/26/2021 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Final 8/26/2021 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 8/26/2021 SGSOV Approved DAVID SANDOVAL
Final 9/14/2021 OK to Issue CofO DAVID SANDOVAL
Green Building Final 9/14/2021 Approved DAVID SANDOVAL