3211 1/2 E GLEASON AVE 90063

Certificate Information: 3211 1/2 E GLEASON AVE 90063

Application / Permit
20014-20000-05609
Plan Check / Job No.
B20VN16214
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
14'8"X8'0" ADDITION AND CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 7/20/2023
Issuing Office
Metro
Current Status
CofO Issued on 5/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/18/2020 APPLICANT
Assigned to Plan Check Engineer 1/14/2021 COLIN LOREDO
Corrections Issued 1/19/2021 COLIN LOREDO
Quality Review Completed 2/9/2021 OMID HEDAYAT
Building Plans Picked Up 2/18/2021 APPLICANT
Plan Check Approved 4/18/2023 MARVEL DELACRUZ
Issued 7/20/2023 APPLICANT
CofO in Progress 5/3/2024 SCOTT FINNILA
Permit Finaled 5/6/2024 DEROLD HAUFF
Permit Finaled 5/6/2024 DEROLD HAUFF
CofO Issued 5/6/2024 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 11/2/2022 ERNEST TSE
Address approval Cleared 11/4/2022 COLIN LOREDO
Roof/Waste drainage to street Cleared 11/4/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 11/7/2022 TREVOR QUAN
Sewer availability Cleared 11/7/2022 TREVOR QUAN
Clean Up Green Up Cleared 11/15/2022 RUBEN VASQUEZ
Construction near power lines Cleared 4/18/2023 TINA MIRANDA
Construction within easement Cleared 4/18/2023 TINA MIRANDA
Grading Pre-Inspection Cleared 4/18/2023 COLIN LOREDO

Contact Information

Contractor Building Blocks Ca Llc; Lic. No.: 1034808-B 180 SOUTH CITRUS AVENUE      LOS ANGELES, CA 90036
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/13/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 9/13/2023 Partial Approval ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 9/25/2023 Corrections Issued FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 9/29/2023 Conditional Approval JUSTIN HAWLEY
Underground Mechanical 9/29/2023 Approved JUSTIN HAWLEY
Excavation/Setback/Form/Re-Bar 10/2/2023 Approved JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 10/13/2023 Partial Approval FREDDIE RIVERA
ELECTRICAL-Rough 10/20/2023 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 10/20/2023 Approved FREDDIE RIVERA
HVAC-Rough 10/20/2023 Partial Inspection FREDDIE RIVERA
PLUMBING-Rough 10/20/2023 Corrections Issued FREDDIE RIVERA
Shower Pan 10/20/2023 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 10/24/2023 Conditional Approval FREDDIE RIVERA
Green Building Rough 10/24/2023 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 10/24/2023 Approved FREDDIE RIVERA
Insulation 11/14/2023 Approved FREDDIE RIVERA
Interior/Exterior Lathing 11/14/2023 Approved FREDDIE RIVERA
Interior/Exterior Lathing 11/22/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 12/13/2023 Approved JUSTIN HAWLEY
Drywall Nailing 12/13/2023 Approved JUSTIN HAWLEY
Green Building Rough 12/13/2023 Approved JUSTIN HAWLEY
HVAC-Rough 12/13/2023 Approved JUSTIN HAWLEY
Final 3/1/2024 Partial Inspection FREDDIE RIVERA
Footing/Foundation/Slab 3/1/2024 Partial Inspection FREDDIE RIVERA
Green Building Final 3/1/2024 Partial Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 3/1/2024 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 3/1/2024 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Final 4/24/2024 Approved SCOTT FINNILA
Final 4/24/2024 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 4/24/2024 Approved SCOTT FINNILA
Green Building Final 4/24/2024 Approved SCOTT FINNILA
HVAC-Final 4/24/2024 Approved SCOTT FINNILA
PLUMBING-Final 4/24/2024 Approved SCOTT FINNILA
Smoke Detectors 4/24/2024 Approved SCOTT FINNILA
Final 5/2/2024 OK to Issue CofO SCOTT FINNILA