8327 1/2 W 4TH ST 90048

Certificate Information: 8327 1/2 W 4TH ST 90048

Application / Permit
20014-20000-05566
Plan Check / Job No.
B20VN16118
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX 19'X32' DET GARAGE INTO ACCESSORY DWELLING UNIT PER ORD #186,481 WITH CANTILEVERED 18'5"X33' 2ND FLR ADDN W/ 5'X28' BALCONY.
Permit Issued
Issued on 3/24/2021
Issuing Office
Current Status
Issued on 3/24/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/15/2020 APPLICANT
Assigned to Plan Check Engineer 12/17/2020 HAYATO TSUCHIYA
Corrections Issued 12/19/2020 HAYATO TSUCHIYA
Quality Review Completed 12/24/2020 STEVEN KIM
Applicant returned to address corrections 3/9/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 3/24/2021 HAYATO TSUCHIYA
Plan Check Approved 3/24/2021 HAYATO TSUCHIYA
Issued 3/24/2021 APPLICANT
Building Plans Picked Up 3/25/2021 APPLICANT

Permit Application Clearance Information

CPC Cleared 12/21/2020 LAUREN PADICK
Address approval Cleared 12/30/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 1/11/2021 JEANIE LAM
Permit Cleared 1/11/2021 JEANIE LAM
Sewer availability Cleared 1/11/2021 JEANIE LAM
Low Impact Development Cleared 2/22/2021 MARTIN FRAGOSO
Construction near power lines Cleared 2/24/2021 WALTER RAMIREZ
Roof/Waste drainage to street Cleared 2/24/2021 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/6/2021 Partial Approval EVAN COOPER
METHANE-Barrier 4/6/2021 Approved EVAN COOPER
METHANE-Subgrade 4/6/2021 Approved EVAN COOPER
Underground Mechanical 4/8/2021 Not Ready for Inspection EVAN COOPER
Footing/Foundation/Slab 4/12/2021 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 4/12/2021 Partial Approval EVAN COOPER
Reinforced Concrete Frame 4/13/2021 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 4/21/2021 Partial Approval EVAN COOPER
Sewer 4/23/2021 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 4/27/2021 Partial Approval EVAN COOPER
PLUMBING-Rough 5/11/2021 Not Ready for Inspection EVAN COOPER
BUILDING-Rough-Frame 5/13/2021 Partial Approval EVAN COOPER
ELECTRICAL-Rough 5/13/2021 Approved EVAN COOPER
PLUMBING-Rough 5/13/2021 Approved EVAN COOPER
BUILDING-Rough-Frame 5/18/2021 Conditional Approval EVAN COOPER
Green Building Rough 5/18/2021 Not Ready for Inspection EVAN COOPER
Insulation 5/18/2021 Corrections Issued EVAN COOPER
METHANE-Rough 5/18/2021 Approved EVAN COOPER
Drywall Nailing 5/27/2021 Not Ready for Inspection EVAN COOPER
Green Building Rough 5/27/2021 Approved EVAN COOPER
Interior/Exterior Lathing 5/27/2021 Partial Approval EVAN COOPER
Shower Pan 5/27/2021 Not Ready for Inspection EVAN COOPER
Drywall Nailing 5/28/2021 Approved EVAN COOPER
ELECTRICAL-Final 7/30/2021 Corrections Issued KEVIN SARGSYAN
Service/Power Release 7/30/2021 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 9/9/2021 Approved EVAN COOPER
Final 9/9/2021 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 9/9/2021 Approved EVAN COOPER
Green Building Final 9/9/2021 Not Ready for Inspection EVAN COOPER
SGSOV-Seismic Gas S/O Valve 9/9/2021 SGSOV Not Ready EVAN COOPER
Smoke Detectors 9/9/2021 Approved EVAN COOPER
ELECTRICAL-Final 9/13/2021 Not Ready for Inspection EVAN COOPER
HVAC-Final 9/13/2021 Not Ready for Inspection EVAN COOPER
PLUMBING-Final 9/13/2021 Not Ready for Inspection EVAN COOPER
Service/Power Release 9/13/2021 Not Ready for Inspection EVAN COOPER
Final 9/20/2021 Corrections Issued EVAN COOPER
SGSOV-Seismic Gas S/O Valve 9/20/2021 SGSOV Not Ready EVAN COOPER
Final 9/28/2021 Corrections Issued EVAN COOPER
Green Building Final 9/28/2021 Not Ready for Inspection EVAN COOPER
SGSOV-Seismic Gas S/O Valve 9/28/2021 SGSOV Not Ready EVAN COOPER