8533-8535 1/2 N CEDROS AVE 91402
Certificate Information: 8533-8535 1/2 N CEDROS AVE 91402
- Application / Permit
- 20014-20000-05564
- Plan Check / Job No.
- B20VN16117
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- ADD 2-UNITS 2-STORY TO (E) 1-STORY SFD CREATING A 3-UNIT 2-STORY TYPE V-B APARTMENT BUILDING (NFPA-13R FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 10/26/2023
- Issuing Office
- Current Status
- Issued on 10/26/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/21/2021 | APPLICANT |
| Green Plans Picked Up | 2/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 2/16/2021 | NILOOFAR MEHRAIN |
| Quality Review Completed | 2/16/2021 | CHON CHIO KUO |
| Building Plans Picked Up | 2/18/2021 | APPLICANT |
| Applicant returned to address corrections | 10/5/2023 | NILOOFAR MEHRAIN |
| Plan Check Approved | 10/26/2023 | NILOOFAR MEHRAIN |
| Issued | 10/26/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/18/2021 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 2/19/2021 | GUILLERMO PETRA |
| Sewer availability | Cleared | 2/19/2021 | GUILLERMO PETRA |
| Trees in Parkway | Cleared | 9/16/2021 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 12/2/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 12/9/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 12/9/2021 | LEE GUILBEAUX |
| Highway dedication | Cleared | 9/12/2023 | DAGOVERTO GUERRERO |
| Permit | Cleared | 9/12/2023 | DAGOVERTO GUERRERO |
| Green Code | Cleared | 10/26/2023 | MICHAEL AYERS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 3/26/2024 | Not Ready for Inspection | ANDREW DORSO |
| Pre-Inspection | 3/26/2024 | Not Ready for Inspection | ANDREW DORSO |
| Wood Frame | 3/26/2024 | Corrections Issued | ANDREW DORSO |
| Excavation/Setback/Form/Re-Bar | 4/9/2024 | Not Ready for Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 7/10/2024 | Not Ready for Inspection | ANDREW DORSO |
| Green Building Rough | 7/15/2024 | Not Ready for Inspection | ANDREW DORSO |
| Excavation/Setback/Form/Re-Bar | 7/18/2024 | Approved | ANDREW DORSO |
| Green Building Rough | 7/18/2024 | Not Ready for Inspection | ANDREW DORSO |
| Wood Frame | 7/18/2024 | Not Ready for Inspection | ANDREW DORSO |
| Pre-Inspection | 8/14/2024 | Partial Inspection | ANDREW DORSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2024 | Partial Inspection | ANDREW DORSO |
| Green Building Rough | 8/23/2024 | Not Ready for Inspection | ANDREW DORSO |
| Pre-Inspection | 8/23/2024 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 8/23/2024 | Partial Inspection | ANDREW DORSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2024 | Partial Inspection | GREGORY POMISH |
| Pre-Inspection | 12/3/2024 | Partial Inspection | GREGORY POMISH |
| Green Building Rough | 1/10/2025 | Not Ready for Inspection | ANDREW DORSO |
| Pre-Inspection | 1/10/2025 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 1/10/2025 | Corrections Issued | ANDREW DORSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2025 | Partial Approval | ANDREW DORSO |
| Interior/Exterior Lathing | 3/25/2025 | Partial Approval | ANDREW DORSO |
| Pre-Inspection | 3/25/2025 | Not Ready for Inspection | ANDREW DORSO |
| Pre-Inspection | 5/8/2026 | Not Ready for Inspection | JOHN KITCKO |
| Green Building Rough | 5/21/2026 | Approved | ROBERT DAVIS |
| Wood Frame | 5/21/2026 | Approved | ROBERT DAVIS |
| Pre-Inspection | 6/15/2026 | Partial Approval | JOHN KITCKO |
| Drywall Nailing | 7/9/2026 | Approved | BRIAN KELLY |