8650 W PINE TREE PL 90069

Certificate Information: 8650 W PINE TREE PL 90069

Application / Permit
20014-20000-05550
Plan Check / Job No.
B20VN16086
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL & ADD TO (E) SFD
Permit Issued
Issued on 5/12/2021
Issuing Office
Current Status
CofO Issued on 2/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/5/2021 APPLICANT
Assigned to Plan Check Engineer 1/7/2021 MOHAMMAD ESMAILI
Corrections Issued 1/9/2021 MOHAMMAD ESMAILI
Quality Review Completed 1/12/2021 OMID HEDAYAT
Building Plans Picked Up 1/13/2021 APPLICANT
Applicant returned to address corrections 3/3/2021 MOHAMMAD ESMAILI
Plan Check Approved 4/26/2021 MOHAMMAD ESMAILI
Issued 5/12/2021 APPLICANT
CofO in Progress 2/6/2025 ROY SPAULDING
Permit Finaled 2/11/2025 DEROLD HAUFF
CofO Issued 2/11/2025 DEROLD HAUFF
Permit Finaled 2/11/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/9/2021 ROSA SILVA
Eng Process Fee Ord 176,300 Cleared 2/10/2021 ROSA SILVA
Distance to fire station Cleared 2/23/2021 KURT CORRAL
Hydrant and Access approval Cleared 2/23/2021 KURT CORRAL
Grading Pre-Inspection Cleared 4/7/2021 MOHAMMAD ESMAILI
Office of Finance Referral Cleared 5/11/2021 MELANIE FLORES

Contact Information

Contractor Dbgc Inc; Lic. No.: 1009448-B 4000 SUNNYSLOPE AVE      SHERMAN OAKS, CA 91423

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 6/1/2021 Conditional Approval RAUL BARAJAS
Deputy Reinf. Concrete 6/2/2021 No Access for Inspection ELMER BLAND
Deputy Reinf. Concrete 6/4/2021 Conditional Approval THOMAS LOGRASSO
Footing/Foundation/Slab 6/8/2021 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 6/9/2021 Conditional Approval RAUL BARAJAS
Deputy Drilled-In Anchors 6/21/2021 No Access for Inspection CHRISTOPHER DELLEFIELD
Deputy Reinf. Concrete 6/21/2021 No Access for Inspection CHRISTOPHER DELLEFIELD
Deputy Drilled-In Anchors 6/22/2021 Conditional Approval ANSON MAGLASANG
Deputy Reinf. Concrete 6/22/2021 Conditional Approval ANSON MAGLASANG
Footing/Foundation/Slab 6/22/2021 Partial Approval RICHARD STEINBACH
Deputy Reinf. Concrete 6/23/2021 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 7/26/2021 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 7/28/2021 Conditional Approval RAUL BARAJAS
Deputy Drilled-In Anchors 8/3/2021 Conditional Approval RAUL BARAJAS
Deputy Reinf. Concrete 9/14/2021 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 10/28/2021 Partial Approval RAUL BARAJAS
Green Building Rough 10/28/2021 Not Ready for Inspection RAUL BARAJAS
Deputy Steel/Welding 11/4/2021 Conditional Approval RAUL BARAJAS
Wood Frame 11/16/2021 Partial Approval ROBERT VORHIS
PLUMBING-Rough 12/1/2021 Approved RAUL BARAJAS
Deputy Steel/Welding 12/23/2021 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 2/10/2022 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 2/16/2022 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 6/22/2022 Conditional Approval RAUL BARAJAS
Deputy Drilled-In Anchors 7/13/2022 Conditional Approval RAUL BARAJAS
Deputy Reinf. Concrete 7/21/2022 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 7/27/2022 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 7/27/2022 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 8/9/2022 Conditional Approval RAUL BARAJAS
Deputy Reinf. Concrete 8/10/2022 Conditional Approval RAUL BARAJAS
Deputy Drilled-In Anchors 8/25/2022 Conditional Approval RUBEN SALAS
Footing/Foundation/Slab 9/1/2022 Partial Approval RAUL BARAJAS
Underground Mechanical 11/7/2022 Approved RAUL BARAJAS
Footing/Foundation/Slab 12/5/2022 Partial Approval RAUL BARAJAS
PLUMBING-Rough 1/9/2023 No Access for Inspection ALIZAH MAYAGOITIA
Deputy Reinf. Concrete 1/30/2023 Conditional Approval STUART CHAPMAN
Footing/Foundation/Slab 2/2/2023 Approved STUART CHAPMAN
PLUMBING-Rough 2/2/2023 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 2/7/2023 Approved STUART CHAPMAN
Deputy Steel/Welding 2/23/2023 Conditional Approval STUART CHAPMAN
Deputy Reinf. Concrete 3/20/2023 Conditional Approval STUART CHAPMAN
Footing/Foundation/Slab 3/23/2023 Approved RAUL BARAJAS
Deputy Drilled-In Anchors 5/18/2023 Conditional Approval STUART CHAPMAN
Deputy Wood Construction 5/18/2023 Conditional Approval STUART CHAPMAN
BUILDING-Rough-Frame 6/29/2023 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 6/29/2023 Partial Approval RAUL BARAJAS
Green Building Rough 6/29/2023 Not Ready for Inspection RAUL BARAJAS
Deputy Reinf. Concrete 8/18/2023 Conditional Approval STUART CHAPMAN
BUILDING-Rough-Frame 8/29/2023 Partial Inspection RAUL BARAJAS
Green Building Rough 8/29/2023 Not Ready for Inspection RAUL BARAJAS
HVAC-Rough 8/29/2023 Partial Inspection RAUL BARAJAS
BUILDING-Rough-Frame 9/7/2023 Partial Inspection RAUL BARAJAS
Green Building Rough 9/7/2023 Approved RAUL BARAJAS
HVAC-Rough 9/7/2023 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 9/22/2023 Partial Approval RAUL BARAJAS
Insulation 9/22/2023 Partial Approval RAUL BARAJAS
Rough-Elec/Plmb/HVAC 9/22/2023 Approved RAUL BARAJAS
BUILDING-Rough-Frame 9/27/2023 Approved STUART CHAPMAN
Insulation 9/27/2023 Approved STUART CHAPMAN
Drywall Nailing 11/14/2023 Approved RAUL BARAJAS
Interior/Exterior Lathing 11/14/2023 Approved RAUL BARAJAS
Drywall Nailing 2/26/2024 Not Ready for Inspection RICHARD DOCKUS
Gas Test 6/26/2024 Partial Approval RICHARD DOCKUS
Gas Test 10/8/2024 Approved JOSH MEISTER
Final 12/16/2024 Corrections Issued ROY SPAULDING
Green Building Final 12/16/2024 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 12/16/2024 SGSOV Approved ROY SPAULDING
Smoke Detectors 12/16/2024 Approved ROY SPAULDING
Final 2/3/2025 OK to Issue CofO ROY SPAULDING