2240 S VETERAN AVE 90064
Certificate Information: 2240 S VETERAN AVE 90064
- Application / Permit
- 20014-20000-05536
- Plan Check / Job No.
- B20VN16054
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT AND ADD 5'0" X 16'9" ADDITION PER LAMC 12.22 A.33(c) and (d). ALL WORK PER ENG.
- Permit Issued
- Issued on 5/5/2021
- Issuing Office
- Current Status
- CofO Issued on 1/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2020 | JEFFREY TANGONAN |
| Corrections Issued | 12/27/2020 | JEFFREY TANGONAN |
| Plan Check Approved | 4/1/2021 | JEFFREY TANGONAN |
| Building Plans Picked Up | 4/5/2021 | APPLICANT |
| Issued | 5/5/2021 | APPLICANT |
| CofO in Progress | 1/24/2022 | KENNETH NAGLE |
| Permit Finaled | 1/24/2022 | KENNETH NAGLE |
| CofO Issued | 1/24/2022 | KENNETH NAGLE |
| Permit Finaled | 1/24/2022 | KENNETH NAGLE |
Permit Application Clearance Information
| Specific Plan | Cleared | 12/29/2020 | MIGUEL GAMBOA |
| Address approval | Cleared | 12/31/2020 | DINAH GARIN |
| Permit | Cleared | 12/31/2020 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 12/31/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 1/5/2021 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 1/5/2021 | BARTON HOLMES |
| Sewer availability | Cleared | 1/5/2021 | DINAH GARIN |
| Specific Plan | Cleared | 2/3/2021 | PEDRO AYALA |
| Construction near power lines | Cleared | 3/20/2021 | RIDWAN HARDY |
Contact Information
| Architect | Yasharel,, Harry H; Lic. No.: C14933 | 4524 WHITE OAK PLACE ENCINO, CA 91316 |
| Contractor | S P S Construction; Lic. No.: 683130-B | 10153 1/2 RIVERSIDE DR APT 463 TOLUCA LAKE, CA 91602 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 5/17/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 5/17/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 5/28/2021 | Partial Approval | KENNETH NAGLE |
| Footing/Foundation/Slab | 6/4/2021 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 6/15/2021 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 6/23/2021 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 6/30/2021 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2021 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 8/19/2021 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2021 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 8/19/2021 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 8/19/2021 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 8/24/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Rough | 8/24/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 8/24/2021 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 8/27/2021 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 8/27/2021 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 8/27/2021 | Partial Approval | KEVIN SARGSYAN |
| Insulation | 8/30/2021 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 9/2/2021 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 9/2/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Shower Pan | 9/17/2021 | Approved | MORRIS JACKSON |
| Shower Pan | 9/21/2021 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 9/22/2021 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 11/15/2021 | Approved | JOHNNY MIRANDA |
| Final | 11/15/2021 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Final | 11/15/2021 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 11/15/2021 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Final | 11/15/2021 | Corrections Issued | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 11/15/2021 | SGSOV Not Ready | JOHNNY MIRANDA |
| Smoke Detectors | 11/15/2021 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 11/23/2021 | SGSOV Not Ready | JOHNNY MIRANDA |
| ELECTRICAL-Final | 12/16/2021 | Approved | JOHNNY MIRANDA |
| Gas Test | 12/16/2021 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 12/16/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Final | 12/16/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Verify Rec and Parks Fee Memo | 12/16/2021 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 12/20/2021 | SGSOV Not Ready | KEVIN SARGSYAN |
| ELECTRICAL-Final | 1/4/2022 | Approved | JOHNNY MIRANDA |
| Final | 1/4/2022 | Partial Approval | JOHNNY MIRANDA |
| HVAC-Final | 1/4/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 1/4/2022 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 1/4/2022 | SGSOV Approved | JOHNNY MIRANDA |
| Service/Power Release | 1/4/2022 | Not Required | JOHNNY MIRANDA |