18919 W ERWIN ST 91335
Certificate Information: 18919 W ERWIN ST 91335
- Application / Permit
- 20014-20000-05535
- Plan Check / Job No.
- B20VN16053
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX DET GARAGE INTO ACCESSORY DWELLING UNIT W/ 15'8"X8' ADDN PER ORD #186.481.
- Permit Issued
- Issued on 1/30/2022
- Issuing Office
- Current Status
- CofO Issued on 3/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 12/27/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 2/10/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 3/7/2021 | HAYATO TSUCHIYA |
| Plan Check Approved | 8/2/2021 | HAYATO TSUCHIYA |
| Issued | 1/30/2022 | APPLICANT |
| Building Plans Picked Up | 2/15/2022 | APPLICANT |
| CofO in Progress | 8/12/2022 | SEAN HAUPT |
| Permit Finaled | 3/13/2023 | DANIEL ORRANTE |
| CofO Issued | 3/13/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/13/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 12/31/2020 | LEE GUILBEAUX |
| Permit | Cleared | 12/31/2020 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 12/31/2020 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 12/31/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/13/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 2/23/2021 | LEE GUILBEAUX |
Contact Information
| Contractor | 123 Restoration Specialists Inc; Lic. No.: 1010734-B | 9556 COZYCROFT AVE CHATSWORTH, CA 91311 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/18/2022 | Partial Approval | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 3/4/2022 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 3/4/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 3/4/2022 | Approved | SEAN HAUPT |
| Underground Mechanical | 3/4/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 3/23/2022 | Approved | SEAN HAUPT |
| HVAC-Rough | 3/23/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 3/23/2022 | Approved | SEAN HAUPT |
| Wood Frame | 3/23/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 4/4/2022 | Partial Approval | VINCENT HANLEY |
| Interior/Exterior Lathing | 4/7/2022 | Approved | SEAN HAUPT |
| Insulation | 4/12/2022 | Approved | MORRIS JACKSON |
| Shower Pan | 4/12/2022 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 4/15/2022 | Approved | SEAN HAUPT |
| Drywall Nailing | 4/15/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 4/15/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 4/15/2022 | Approved | SEAN HAUPT |
| Pre-Inspection | 5/12/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 6/22/2022 | Approved | SEAN HAUPT |
| Final | 6/22/2022 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 6/22/2022 | Not Ready for Inspection | SEAN HAUPT |
| HVAC-Final | 6/22/2022 | Approved | SEAN HAUPT |
| PLUMBING-Final | 6/22/2022 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 6/22/2022 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 6/22/2022 | Approved | SEAN HAUPT |
| Final | 7/19/2022 | Partial Inspection | JUSTIN HAWLEY |
| Green Building Final | 7/19/2022 | Partial Inspection | JUSTIN HAWLEY |
| Final | 8/11/2022 | OK to Issue CofO | SEAN HAUPT |
| Green Building Final | 8/11/2022 | Approved | SEAN HAUPT |