3731 N BOBSTONE DR 91423

Certificate Information: 3731 N BOBSTONE DR 91423

Application / Permit
20014-20000-05531
Plan Check / Job No.
B20VN16046
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 10'X7'6" MASTER CLOSET ADDITION W/ 3'6" CANTILEVER ROOF PROJECTION AT REAR PER ENGR DESIGN.
Permit Issued
Issued on 4/20/2021
Issuing Office
Current Status
CofO Issued on 10/30/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/16/2020 APPLICANT
Assigned to Plan Check Engineer 12/30/2020 HAYATO TSUCHIYA
Corrections Issued 1/3/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 3/5/2021 HAYATO TSUCHIYA
Building Plans Picked Up 3/5/2021 APPLICANT
Plan Check Approved 4/7/2021 PETER MOSESIAN
Issued 4/20/2021 APPLICANT
CofO in Progress 10/20/2021 MISAEL ESPARZA
CofO Issued 10/30/2021 MICHAEL SMITH
Permit Finaled 10/30/2021 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/7/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/8/2021 ADRIAN CASTRO
Grading Pre-Inspection Cleared 1/15/2021 BARTON HOLMES
Specific Plan Cleared 2/5/2021 OLGA AYALA

Contact Information

Contractor A List Builders Inc; Lic. No.: 952112-B 13237 CHANDLER BLVD      SHERMAN OAKS, CA 91401
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22121 CLARENDON ST APT 340      WOODLAND HILLS, CA 91367

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/10/2021 Partial Approval CHARLES POWELL
Excavation/Setback/Form/Re-Bar 5/13/2021 Approved CHARLES POWELL
Footing/Foundation/Slab 5/13/2021 Approved CHARLES POWELL
BUILDING-Rough-Frame 6/8/2021 Not Ready for Inspection CHARLES POWELL
ELECTRICAL-Rough 6/8/2021 Approved CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 6/8/2021 Approved CHARLES POWELL
Green Building Rough 6/8/2021 Not Ready for Inspection CHARLES POWELL
BUILDING-Rough-Frame 7/8/2021 Approved CHARLES POWELL
Green Building Rough 7/8/2021 Not Ready for Inspection CHARLES POWELL
Insulation 7/14/2021 Approved CHARLES POWELL
Interior/Exterior Lathing 7/14/2021 Approved CHARLES POWELL
Drywall Nailing 7/19/2021 Approved JAVIER RAMOS JR
Green Building Rough 7/19/2021 Approved JAVIER RAMOS JR
Final 8/25/2021 Corrections Issued CHARLES POWELL
Green Building Final 8/25/2021 Approved CHARLES POWELL
SGSOV-Seismic Gas S/O Valve 8/25/2021 SGSOV Not Ready CHARLES POWELL
Smoke Detectors 8/25/2021 Corrections Issued CHARLES POWELL
SGSOV-Seismic Gas S/O Valve 9/30/2021 SGSOV Not Ready MISAEL ESPARZA
Final 10/7/2021 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 10/7/2021 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 10/7/2021 Approved MISAEL ESPARZA
ELECTRICAL-Final 10/19/2021 Approved MISAEL ESPARZA
Final 10/19/2021 OK to Issue CofO MISAEL ESPARZA
HVAC-Final 10/19/2021 Approved MISAEL ESPARZA
PLUMBING-Final 10/19/2021 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 10/19/2021 SGSOV Approved MISAEL ESPARZA