5454 N BUFFALO AVE 91401
Certificate Information: 5454 N BUFFALO AVE 91401
- Application / Permit
- 20014-20000-05514
- Plan Check / Job No.
- B20VN16016
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 36'-3" X 30'-3" IRREGULAR SHAPED ADDITION TO REAR OF EXISTING SINGLE FAMILY DWELLING; 7'-5" X 9'-8" TO FRONT OF DWELLING; INTERIOR REMODEL; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 1/4/2022
- Issuing Office
- Current Status
- CofO Corrected on 6/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2021 | SELLA BENYAMIN |
| Corrections Issued | 1/11/2021 | SELLA BENYAMIN |
| Quality Review Completed | 1/15/2021 | STEVEN KIM |
| Building Plans Picked Up | 1/15/2021 | APPLICANT |
| Plan Check Approved | 11/16/2021 | SELLA BENYAMIN |
| Issued | 1/4/2022 | APPLICANT |
| CofO in Progress | 12/27/2024 | RYAN SALAZAR |
| CofO Issued-Status Void | 1/7/2025 | RUBEN SALAS |
| Permit Finaled-Status Void | 1/7/2025 | RUBEN SALAS |
| Re-Activate Permit | 6/5/2025 | RUBEN SALAS |
| Permit Finaled | 6/17/2025 | RUBEN SALAS |
| CofO Corrected | 6/17/2025 | RUBEN SALAS |
| Permit Finaled | 6/17/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/22/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 6/22/2021 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 10/15/2021 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 10/19/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/15/2024 | Partial Inspection | RYAN SALAZAR |
| PLUMBING-Rough | 4/22/2024 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 6/17/2024 | Approved | RYAN SALAZAR |
| HVAC-Rough | 6/17/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 6/17/2024 | Partial Approval | RYAN SALAZAR |
| Shower Pan | 6/21/2024 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 6/28/2024 | Approved | RYAN SALAZAR |
| Green Building Rough | 6/28/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 6/28/2024 | Approved | RYAN SALAZAR |
| Wood Frame | 6/28/2024 | Approved | RYAN SALAZAR |
| Insulation | 7/1/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 7/1/2024 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 7/5/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 7/5/2024 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 12/12/2024 | Approved | RYAN SALAZAR |
| HVAC-Final | 12/12/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 12/12/2024 | Approved | RYAN SALAZAR |
| Service/Power Release | 12/12/2024 | Approved | RYAN SALAZAR |
| Final | 12/26/2024 | OK to Issue CofO | RYAN SALAZAR |
| Footing/Foundation/Slab | 12/26/2024 | Approved | RYAN SALAZAR |
| Green Building Final | 12/26/2024 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 12/26/2024 | SGSOV Approved | RYAN SALAZAR |
| Service/Power Release | 12/26/2024 | Partial Inspection | RYAN SALAZAR |
| Smoke Detectors | 12/26/2024 | Approved | RYAN SALAZAR |