13042 N JOLETTE AVE 91344
Certificate Information: 13042 N JOLETTE AVE 91344
- Application / Permit
- 20014-20000-05503
- Plan Check / Job No.
- B20VN15989
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1ST AND 2ND STORY ADDITION TO (E) SINGLE FAMILY DWELLING, CONVERT PORTION OF (E) GARAGE TO LAUNDRY. NFPA 13-D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/1/2021
- Issuing Office
- Current Status
- CofO Issued on 1/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2021 | COLIN LOREDO |
| Corrections Issued | 1/12/2021 | COLIN LOREDO |
| Quality Review Completed | 1/22/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 1/26/2021 | APPLICANT |
| Plan Check Approved | 4/1/2021 | COLIN LOREDO |
| Issued | 4/1/2021 | APPLICANT |
| CofO in Progress | 1/6/2022 | DAVID SCANTLIN |
| Permit Finaled | 1/6/2022 | JOHN JANSON |
| CofO Issued | 1/6/2022 | JOHN JANSON |
| Permit Finaled | 1/6/2022 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/8/2021 | GUILLERMO PETRA |
| Sewer availability | Cleared | 1/8/2021 | GUILLERMO PETRA |
| ZA Case | Cleared | 1/8/2021 | MIGUEL GAMBOA |
| ZA Case | Cleared | 1/8/2021 | MIGUEL GAMBOA |
| BHO/Hillside ordinance | Cleared | 2/1/2021 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 2/1/2021 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 2/1/2021 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 2/1/2021 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 2/1/2021 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 2/18/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 3/18/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 3/18/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 4/8/2021 | Partial Approval | DAVID SCANTLIN |
| Pre-Inspection | 4/8/2021 | Approved | DAVID SCANTLIN |
| Deputy Drilled-In Anchors | 4/15/2021 | Approved | DAVID SCANTLIN |
| Footing/Foundation/Slab | 4/15/2021 | Approved | DAVID SCANTLIN |
| METHANE-Barrier | 4/15/2021 | Approved | DAVID SCANTLIN |
| METHANE-Subgrade | 4/15/2021 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2021 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 5/7/2021 | Not Ready for Inspection | SEAN WIRCH |
| ELECTRICAL-Rough | 5/7/2021 | Not Ready for Inspection | SEAN WIRCH |
| Green Building Rough | 5/7/2021 | Not Ready for Inspection | SEAN WIRCH |
| HVAC-Rough | 5/7/2021 | Not Ready for Inspection | SEAN WIRCH |
| METHANE-Rough | 5/7/2021 | Approved | SEAN WIRCH |
| PLUMBING-Rough | 5/7/2021 | Not Ready for Inspection | SEAN WIRCH |
| Verify Sprinkler Sign Off | 5/7/2021 | Not Ready for Inspection | SEAN WIRCH |
| Wood Frame | 5/7/2021 | Not Ready for Inspection | SEAN WIRCH |
| BUILDING-Rough-Frame | 5/13/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2021 | Approved | DAVID SCANTLIN |
| Green Building Rough | 5/13/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| HVAC-Rough | 5/13/2021 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 5/13/2021 | Approved | DAVID SCANTLIN |
| Rough-Elec/Plmb/HVAC | 5/13/2021 | Approved | DAVID SCANTLIN |
| Shower Pan | 5/13/2021 | Approved | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 5/13/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Wood Frame | 5/13/2021 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 5/24/2021 | Approved | DAVID SCANTLIN |
| Light Gage Steel Frame | 5/24/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Shower Pan | 5/24/2021 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 6/2/2021 | Approved | DAVID SCANTLIN |
| Green Building Rough | 6/2/2021 | Approved | DAVID SCANTLIN |
| Insulation | 6/2/2021 | Approved | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 6/2/2021 | Approved | DAVID SCANTLIN |
| Wood Frame | 6/2/2021 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 6/9/2021 | Partial Approval | LILIANA PORTILLO |
| Interior/Exterior Lathing | 6/9/2021 | Partial Approval | LILIANA PORTILLO |
| Drywall Nailing | 7/27/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Underground Mechanical | 7/27/2021 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 8/17/2021 | Approved | DAVID SCANTLIN |
| Underground Mechanical | 8/17/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Wood Frame | 8/17/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 1/5/2022 | OK to Issue CofO | DAVID SCANTLIN |
| Green Building Final | 1/5/2022 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 1/5/2022 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 1/5/2022 | Approved | DAVID SCANTLIN |