1345 N LONDONDERRY PL 90069
Certificate Information: 1345 N LONDONDERRY PL 90069
- Application / Permit
- 20014-20000-05502
- Plan Check / Job No.
- B20VN15987
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL & ADDITION TO (E) SINGLE FAMILY DWELLING, CONVERT (E) GARAGE TO LIVING AREA, & ADD NEW, ATTACHED GARAGE. NFPA 13-D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/22/2021
- Issuing Office
- Current Status
- CofO Issued on 6/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2021 | COLIN LOREDO |
| Corrections Issued | 1/12/2021 | COLIN LOREDO |
| Quality Review Completed | 1/28/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 2/3/2021 | APPLICANT |
| Applicant returned to address corrections | 3/11/2021 | COLIN LOREDO |
| Applicant returned to address corrections | 3/23/2021 | COLIN LOREDO |
| Applicant returned to address corrections | 7/6/2021 | COLIN LOREDO |
| Plan Check Approved | 9/8/2021 | COLIN LOREDO |
| Issued | 9/22/2021 | APPLICANT |
| CofO in Progress | 6/12/2023 | RAUL BARAJAS |
| Permit Finaled | 6/28/2023 | DEROLD HAUFF |
| CofO Issued | 6/28/2023 | DEROLD HAUFF |
| Permit Finaled | 6/28/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 3/8/2021 | RENZ SORIANO |
| BHO/Hillside ordinance | Cleared | 3/8/2021 | RENZ SORIANO |
| BHO/Hillside ordinance | Cleared | 3/8/2021 | RENZ SORIANO |
| BHO/Hillside ordinance | Cleared | 3/8/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 3/8/2021 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 3/10/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 3/10/2021 | RENZ SORIANO |
| Hydrant and Access approval | Cleared | 3/24/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 4/21/2021 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 4/22/2021 | ROSA SILVA |
| Construction near power lines | Cleared | 6/25/2021 | RIDWAN HARDY |
| Miscellaneous | Cleared | 8/31/2021 | ALBERT TAM |
| Drainage to Storm Drain | Cleared | 9/1/2021 | ARMEN MEHRABIAN |
Contact Information
| Contractor | Precision Building Corp; Lic. No.: 771675-B | 2785 PACIFIC COAST HWY STE E # 418 TORRANCE, CA 90505 |
| Engineer | Mani,, Dev; Lic. No.: C62778 | P O BOX 1451 DUARTE, CA 91009 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 10/8/2021 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 10/8/2021 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 10/13/2021 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 11/15/2021 | Approved | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 3/3/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Wood Construction | 3/3/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Wood Construction | 3/8/2022 | Conditional Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 3/17/2022 | Approved | RAUL BARAJAS |
| HVAC-Rough | 3/17/2022 | Corrections Issued | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2022 | Partial Approval | RAUL BARAJAS |
| HVAC-Rough | 3/25/2022 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 3/25/2022 | Conditional Approval | RAUL BARAJAS |
| Wood Frame | 3/25/2022 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 4/6/2022 | Corrections Issued | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2022 | Approved | RAUL BARAJAS |
| HVAC-Rough | 4/6/2022 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 4/6/2022 | Approved | RAUL BARAJAS |
| Wood Frame | 4/6/2022 | Conditional Approval | RAUL BARAJAS |
| Green Building Rough | 4/8/2022 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 4/22/2022 | Approved | RAUL BARAJAS |
| Insulation | 4/27/2022 | Corrections Issued | RAUL BARAJAS |
| Drywall Nailing | 5/4/2022 | Approved | RAUL BARAJAS |
| Insulation | 5/4/2022 | Approved | RAUL BARAJAS |
| Shower Pan | 5/31/2022 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 6/7/2022 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 8/16/2022 | Corrections Issued | RAUL BARAJAS |
| HVAC-Final | 8/19/2022 | Corrections Issued | RAUL BARAJAS |
| Gas Test | 8/22/2022 | Approved | RAUL BARAJAS |
| PLUMBING-Final | 8/22/2022 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Final | 8/31/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Service/Power Release | 8/31/2022 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 9/8/2022 | Approved | RAUL BARAJAS |
| PLUMBING-Final | 9/8/2022 | Approved | RAUL BARAJAS |
| Special/Order Compliance | 10/6/2022 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 10/13/2022 | Approved | RAUL BARAJAS |
| Final | 10/13/2022 | Corrections Issued | RAUL BARAJAS |
| Green Building Final | 10/13/2022 | Approved | RAUL BARAJAS |
| HVAC-Final | 10/13/2022 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 10/13/2022 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 10/13/2022 | Approved | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 10/13/2022 | Approved | RAUL BARAJAS |
| Final | 6/12/2023 | OK to Issue CofO | RAUL BARAJAS |