1520 N TONAWANDA AVE 90041

Certificate Information: 1520 N TONAWANDA AVE 90041

Application / Permit
20014-20000-05492
Plan Check / Job No.
B20VN15977
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL AND FRONT PORCH ENCLOSURE AND (N) PORCH ADDITION (8'-0"X3'-6") TO THE (E) SFD. AND RE-ROOFING FIRE SPRINKLER NFPA-13D
Permit Issued
Issued on 5/19/2021
Issuing Office
Current Status
CofO Issued on 3/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/13/2021 APPLICANT
Assigned to Plan Check Engineer 2/3/2021 MOHAMMAD ESMAILI
Corrections Issued 2/4/2021 MOHAMMAD ESMAILI
Building Plans Picked Up 2/11/2021 APPLICANT
Plan Check Approved 5/2/2021 MOHAMMAD ESMAILI
Issued 5/19/2021 APPLICANT
CofO in Progress 3/14/2024 CRAIG VAUGHAN
CofO Issued 3/19/2024 DEROLD HAUFF
Permit Finaled 3/19/2024 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/16/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 2/17/2021 JEANIE LAM
Grading Pre-Inspection Cleared 2/17/2021 BRIAN MILLER
Tenant Habitability Plan Cleared 3/25/2021 MICHAEL SOTO

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/8/2021 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 6/22/2021 Approved CRAIG VAUGHAN
Deputy Wood Construction 9/3/2021 No Access for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 1/6/2022 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 1/6/2022 Corrections Issued CRAIG VAUGHAN
HVAC-Rough 1/6/2022 Approved CRAIG VAUGHAN
PLUMBING-Rough 1/6/2022 Approved CRAIG VAUGHAN
Wood Frame 1/13/2022 Corrections Issued CRAIG VAUGHAN
BUILDING-Rough-Frame 2/2/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 2/2/2022 Approved CRAIG VAUGHAN
Green Building Rough 2/2/2022 Approved CRAIG VAUGHAN
Wood Frame 2/2/2022 Approved CRAIG VAUGHAN
Insulation 2/9/2022 Approved CRAIG VAUGHAN
Drywall Nailing 2/11/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Drywall Nailing 2/16/2022 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 4/7/2022 SGSOV Not Ready CRAIG VAUGHAN
Insulation 4/11/2022 Approved CRAIG VAUGHAN
Final 4/15/2022 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 4/15/2022 Approved CRAIG VAUGHAN
Green Building Final 4/15/2022 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 4/15/2022 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 4/15/2022 Approved CRAIG VAUGHAN
Final 8/21/2023 Conditional Approval CRAIG VAUGHAN
Final 3/13/2024 OK to Issue CofO CRAIG VAUGHAN