8225 N FALLBROOK AVE 91304

Certificate Information: 8225 N FALLBROOK AVE 91304

Application / Permit
20014-20000-05486
Plan Check / Job No.
B20VN15968
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
24' X 19' 5" BEDROOM/BATHROOM/CLOSET ADDITION AND 6' X 6' 7" PORCH ADDITION TO FRONT OF (E) SFD. ALL WORK DOEN PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 3/29/2021
Issuing Office
Current Status
CofO Issued on 9/9/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/11/2020 APPLICANT
Assigned to Plan Check Engineer 12/23/2020 GURUNATH NESARAJAH
Corrections Issued 12/26/2020 GURUNATH NESARAJAH
Applicant returned to address corrections 2/1/2021 GURUNATH NESARAJAH
Applicant returned to address corrections 3/4/2021 GURUNATH NESARAJAH
Plan Check Approved 3/26/2021 GURUNATH NESARAJAH
Issued 3/29/2021 APPLICANT
Building Plans Picked Up 3/31/2021 APPLICANT
CofO in Progress 8/26/2021 DAVID STEPANYAN
Permit Finaled 9/9/2021 JOHN JANSON
CofO Issued 9/9/2021 JOHN JANSON
Permit Finaled 9/9/2021 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/21/2021 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 1/21/2021 ADRIAN CASTRO
Sewer availability Cleared 3/18/2021 GABRIEL ROBLES

Contact Information

Contractor A To Z Construction Inc; Lic. No.: 988824-B 22759 CAVALIER ST      WOODLAND HILLS, CA 91364
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/7/2021 Approved DAVID STEPANYAN
PLUMBING-Rough 5/7/2021 Partial Approval DAVID STEPANYAN
Sewer 5/7/2021 Approved DAVID STEPANYAN
BUILDING-Rough-Frame 6/7/2021 Corrections Issued DAVID STEPANYAN
ELECTRICAL-Rough 6/7/2021 Corrections Issued DAVID STEPANYAN
PLUMBING-Rough 6/7/2021 Corrections Issued DAVID STEPANYAN
Shower Pan 6/11/2021 Approved RONALD COWAN
Wood Frame 6/11/2021 Partial Approval RONALD COWAN
BUILDING-Rough-Frame 6/23/2021 Approved DAVID STEPANYAN
Green Building Rough 6/23/2021 Approved DAVID STEPANYAN
Interior/Exterior Lathing 6/23/2021 Approved DAVID STEPANYAN
Rough-Elec/Plmb/HVAC 6/23/2021 Approved DAVID STEPANYAN
Insulation 6/29/2021 Approved SHAVONNE ESPINOZA
Drywall Nailing 7/2/2021 Not Ready for Inspection SHAVONNE ESPINOZA
Drywall Nailing 7/8/2021 Approved RYAN SALAZAR
Final 8/13/2021 Not Ready for Inspection DAVID STEPANYAN
Green Building Final 8/13/2021 Corrections Issued DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 8/13/2021 SGSOV Approved DAVID STEPANYAN
Smoke Detectors 8/13/2021 Corrections Issued DAVID STEPANYAN
Final 8/23/2021 Partial Approval JEFFREY PARD
Green Building Final 8/23/2021 Approved JEFFREY PARD
Smoke Detectors 8/23/2021 Approved JEFFREY PARD
Final 8/26/2021 OK to Issue CofO DAVID STEPANYAN