10214 N TOPEKA DR 91324
Certificate Information: 10214 N TOPEKA DR 91324
- Application / Permit
- 20014-20000-05471
- Plan Check / Job No.
- B20VN15941
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD IRREGULAR SHAPED 35'-6" x 9'-2" TO (E) S.F.D. PER WFPP
- Permit Issued
- Issued on 11/4/2021
- Issuing Office
- Current Status
- CofO Issued on 1/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/21/2020 | ALFRED RAMIREZ |
| Corrections Issued | 12/21/2020 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 5/13/2021 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 5/19/2021 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 5/20/2021 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 5/27/2021 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 8/18/2021 | ALFRED RAMIREZ |
| Issued | 11/4/2021 | APPLICANT |
| Building Plans Picked Up | 11/12/2021 | APPLICANT |
| CofO in Progress | 1/9/2023 | JOHN KIDWELL |
| Permit Finaled | 1/9/2023 | JOHN JANSON |
| CofO Issued | 1/9/2023 | JOHN JANSON |
| Permit Finaled | 1/9/2023 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/8/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/9/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/25/2022 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 3/7/2022 | Partial Approval | JEFFREY PARD |
| Green Building Rough | 3/7/2022 | Not Ready for Inspection | JEFFREY PARD |
| PLUMBING-Rough | 3/7/2022 | Partial Approval | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2022 | Partial Approval | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2022 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 5/23/2022 | Approved | JEFFREY PARD |
| Drywall Nailing | 5/23/2022 | Not Ready for Inspection | JEFFREY PARD |
| ELECTRICAL-Rough | 5/23/2022 | Approved | JEFFREY PARD |
| Green Building Rough | 5/23/2022 | Not Ready for Inspection | JEFFREY PARD |
| HVAC-Rough | 5/23/2022 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 5/23/2022 | Approved | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2022 | Approved | JEFFREY PARD |
| Insulation | 6/16/2022 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 6/16/2022 | Approved | JEFFREY PARD |
| Drywall Nailing | 7/18/2022 | Approved | MORRIS JACKSON |
| Green Building Rough | 7/18/2022 | Approved | MORRIS JACKSON |
| Shower Pan | 8/31/2022 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 9/23/2022 | Approved | KRISTEN CAUSEY |
| Footing/Foundation/Slab | 12/7/2022 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 12/7/2022 | SGSOV Not Ready | JOHN KIDWELL |
| Smoke Detectors | 12/7/2022 | Corrections Issued | JOHN KIDWELL |
| Final | 12/27/2022 | OK to Issue CofO | JOHN KIDWELL |
| Green Building Final | 12/27/2022 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 12/27/2022 | SGSOV Approved | JOHN KIDWELL |
| Smoke Detectors | 12/27/2022 | Approved | JOHN KIDWELL |