6424 N SALE AVE 91307

Certificate Information: 6424 N SALE AVE 91307

Application / Permit
20014-20000-05453
Plan Check / Job No.
B20VN15898
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT OF (E) GARAGE/STORAGE WITH ADDITION TO CREATE NEW ACCESSORY DWELLING UNIT per AMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 7/6/2021
Issuing Office
Current Status
CofO Corrected on 6/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/22/2020 APPLICANT
Assigned to Plan Check Engineer 1/14/2021 MOHAMMAD ESMAILI
Plans on Hold 1/26/2021 MOHAMMAD ESMAILI
Hold Released 2/23/2021 MOHAMMAD ESMAILI
Corrections Issued 2/23/2021 MOHAMMAD ESMAILI
Quality Review Completed 3/1/2021 OMID HEDAYAT
Building Plans Picked Up 3/2/2021 APPLICANT
Plan Check Approved 6/30/2021 MOHAMMAD ESMAILI
Issued 7/6/2021 APPLICANT
CofO in Progress 6/15/2022 TROY SANDERS
Re-Activate Permit 6/30/2022 JOHN JANSON
Permit Finaled-Status Void 6/30/2022 JOHN JANSON
CofO Issued-Status Void 6/30/2022 JOHN JANSON
CofO Corrected 6/30/2022 JOHN JANSON
Permit Finaled 6/30/2022 JOHN JANSON

Permit Application Clearance Information

Hold Cleared 2/8/2021 JASON SHEETS
Address approval Cleared 3/15/2021 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 3/15/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/15/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 3/17/2021 JOHN TRIANTAFYLLOS
Grading Pre-Inspection Cleared 3/30/2021 BRIAN MILLER
Construction near power lines Cleared 6/29/2021 JOHN BACON
GPI Written Notices Cleared 6/29/2021 MOHAMMAD ESMAILI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/29/2021 Approved TROY SANDERS
Deputy Drilled-In Anchors 8/12/2021 Conditional Approval STEPHANIE SWANSON
Footing/Foundation/Slab 10/14/2021 Approved TROY SANDERS
PLUMBING-Rough 10/14/2021 Partial Approval TROY SANDERS
ELECTRICAL-Rough 1/27/2022 Not Ready for Inspection MORRIS JACKSON
PLUMBING-Rough 1/27/2022 Not Ready for Inspection MORRIS JACKSON
Sewer 1/27/2022 Not Ready for Inspection MORRIS JACKSON
BUILDING-Rough-Frame 2/2/2022 Partial Approval TROY SANDERS
Rough-Elec/Plmb/HVAC 2/2/2022 Partial Approval TROY SANDERS
ELECTRICAL-Rough 2/28/2022 No Access for Inspection TROY SANDERS
HVAC-Rough 2/28/2022 No Access for Inspection TROY SANDERS
PLUMBING-Rough 2/28/2022 No Access for Inspection TROY SANDERS
Rough-Elec/Plmb/HVAC 2/28/2022 No Access for Inspection TROY SANDERS
ELECTRICAL-Rough 3/15/2022 Approved TROY SANDERS
HVAC-Rough 3/15/2022 Approved TROY SANDERS
PLUMBING-Rough 3/15/2022 Approved TROY SANDERS
BUILDING-Rough-Frame 3/22/2022 Approved TROY SANDERS
Green Building Rough 3/22/2022 Approved TROY SANDERS
Insulation 3/22/2022 Approved TROY SANDERS
Drywall Nailing 4/5/2022 Approved JESUS PINEDA
Drywall Nailing 4/8/2022 Approved MORRIS JACKSON
Final 6/14/2022 OK to Issue CofO TROY SANDERS
Green Building Final 6/14/2022 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 6/14/2022 SGSOV Approved TROY SANDERS
Smoke Detectors 6/14/2022 Approved TROY SANDERS