1219 S WINDSOR BLVD 90019

Certificate Information: 1219 S WINDSOR BLVD 90019

Application / Permit
20014-20000-05437
Plan Check / Job No.
B20VN15857
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 19'-10" X 20'-2" DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(A). ALL WORK PER WFPP.
Permit Issued
Issued on 2/2/2022
Issuing Office
Current Status
CofO Issued on 11/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/8/2020 APPLICANT
Assigned to Plan Check Engineer 12/25/2020 JENNIFER LEE
Corrections Issued 12/28/2020 JENNIFER LEE
Applicant returned to address corrections 9/2/2021 JENNIFER LEE
Applicant returned to address corrections 12/7/2021 JENNIFER LEE
Plan Check Approved 2/1/2022 JENNIFER LEE
Issued 2/2/2022 APPLICANT
Building Plans Picked Up 2/7/2022 APPLICANT
CofO in Progress 11/17/2022 STUART CHAPMAN
CofO in Progress 11/18/2022 STUART CHAPMAN
Permit Finaled 11/19/2022 DEROLD HAUFF
CofO Issued 11/19/2022 DEROLD HAUFF
Permit Finaled 11/19/2022 DEROLD HAUFF

Permit Application Clearance Information

Miscellaneous Cleared 2/17/2021 LAUREN PADICK
Address approval Cleared 2/19/2021 JEANIE LAM
HPOZ Cleared 2/19/2021 AMANDA KAINER
Miscellaneous Cleared 2/19/2021 AMANDA KAINER
ZI Cleared 2/19/2021 AMANDA KAINER
Eng Process Fee Ord 176,300 Cleared 3/1/2021 JEANIE LAM
Sewer availability Cleared 3/1/2021 JEANIE LAM

Contact Information

Contractor Sound Structures Inc; Lic. No.: 923028-B 21017 HILLSIDE DRIVE      TOPANGA, CA 90290

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/24/2022 Approved STUART CHAPMAN
Footing/Foundation/Slab 3/4/2022 Approved RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 3/10/2022 Partial Approval STUART CHAPMAN
Sewer 3/16/2022 Approved STUART CHAPMAN
Underground Mechanical 3/16/2022 Approved STUART CHAPMAN
ELECTRICAL-Rough 3/23/2022 Approved STUART CHAPMAN
PLUMBING-Rough 3/23/2022 Approved STUART CHAPMAN
Insulation 3/25/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 3/25/2022 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 3/29/2022 Approved STUART CHAPMAN
HVAC-Rough 3/29/2022 Approved STUART CHAPMAN
Drywall Nailing 4/1/2022 Approved KATHRYN BUTTERWORTH
Green Building Rough 4/1/2022 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 6/17/2022 Approved STUART CHAPMAN
ELECTRICAL-Final 6/17/2022 Approved STUART CHAPMAN
Final 6/17/2022 Partial Approval STUART CHAPMAN
Green Building Final 6/17/2022 Approved STUART CHAPMAN
HVAC-Final 6/17/2022 Approved STUART CHAPMAN
METHANE-Final 6/17/2022 Approved STUART CHAPMAN
METHANE-Rough 6/17/2022 Approved STUART CHAPMAN
PLUMBING-Final 6/17/2022 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 6/17/2022 SGSOV Approved STUART CHAPMAN
Smoke Detectors 6/17/2022 Approved STUART CHAPMAN
Final 11/17/2022 OK to Issue CofO STUART CHAPMAN
Service/Power Release 11/17/2022 Approved STUART CHAPMAN