10538 N AQUEDUCT AVE 91344

Certificate Information: 10538 N AQUEDUCT AVE 91344

Application / Permit
20014-20000-05434
Plan Check / Job No.
B20VN15843
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 16'-6" X 29'-3" IRREGULAR SHAPED ADDITION TO (E) SFD FOR (N) BEDROOMS, BATHROOMS, AND CLOSETS. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 2/16/2021
Issuing Office
Current Status
CofO Issued on 4/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/14/2020 APPLICANT
Assigned to Plan Check Engineer 12/23/2020 RAPHAEL ROSAS
Corrections Issued 12/27/2020 RAPHAEL ROSAS
Plan Check Approved 1/22/2021 RAPHAEL ROSAS
Issued 2/16/2021 APPLICANT
CofO in Progress 4/21/2025 RAUL OLAGI
Permit Finaled 4/24/2025 RUBEN SALAS
CofO Issued 4/24/2025 RUBEN SALAS
Permit Finaled 4/24/2025 RUBEN SALAS

Permit Application Clearance Information

Sewer availability Cleared 1/12/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/14/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 1/29/2021 GABRIEL ROBLES

Contact Information

Engineer Ostowari,, Sohrab; Lic. No.: C41014 7012 HELMSDALE RD      WEST HILLS, CA 91307

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/18/2021 No Access for Inspection MARK JOHNSON
Footing/Foundation/Slab 2/19/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 3/3/2021 Corrections Issued MARK JOHNSON
Green Building Rough 3/3/2021 Not Ready for Inspection MARK JOHNSON
MERV13>=Rough 3/3/2021 Not Ready for Inspection MARK JOHNSON
BUILDING-Rough-Frame 3/11/2021 Partial Approval MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 3/11/2021 Partial Approval MARK JOHNSON
PLUMBING-Rough 3/11/2021 Partial Approval MARK JOHNSON
ELECTRICAL-Rough 3/16/2021 Approved MARK JOHNSON
HVAC-Rough 3/16/2021 Partial Approval MARK JOHNSON
PLUMBING-Rough 3/16/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 3/22/2021 Approved MARK JOHNSON
Green Building Rough 3/22/2021 Approved MARK JOHNSON
HVAC-Rough 3/22/2021 Approved MARK JOHNSON
Insulation 3/22/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 3/22/2021 Approved MARK JOHNSON
MERV13>=Rough 3/22/2021 Approved MARK JOHNSON
Drywall Nailing 3/26/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 3/26/2021 Approved MARK JOHNSON
Shower Pan 3/26/2021 Approved MARK JOHNSON
Final 4/30/2021 Corrections Issued MARK JOHNSON
Green Building Final 4/30/2021 Approved MARK JOHNSON
MERV13>=Final 4/30/2021 Approved MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 4/30/2021 SGSOV Approved MARK JOHNSON
Smoke Detectors 4/30/2021 Approved MARK JOHNSON
Final 4/21/2025 OK to Issue CofO RAUL OLAGI