5213 N BILOXI AVE 91601

Certificate Information: 5213 N BILOXI AVE 91601

Application / Permit
20014-20000-05416
Plan Check / Job No.
B20VN15778
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 8'-3" X 18'-2" GARDEN HOUSE AND ADD 7'-9" X 18'-2" FOR NEW ACCESSORY DWELLING UNIT W/ ATTIC STORAGE SPACE PER 65852.2(E)(1)(B); (E) ATTACHED GARAGE TO REMAIN. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 4/7/2021
Issuing Office
Current Status
CofO Issued on 2/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/7/2020 APPLICANT
Assigned to Plan Check Engineer 12/15/2020 JENNIFER LEE
Corrections Issued 12/16/2020 JENNIFER LEE
Plan Check Approved 4/7/2021 JENNIFER LEE
Issued 4/7/2021 APPLICANT
Building Plans Picked Up 5/4/2021 APPLICANT
CofO in Progress 2/6/2022 CHRISTOPHE COCHRAN
CofO in Progress 2/8/2022 CHRISTOPHE COCHRAN
CofO Issued 2/15/2022 MICHAEL SMITH
Permit Finaled 2/15/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 2/10/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 2/10/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 2/10/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 2/11/2021 LEE GUILBEAUX
Sewer availability Cleared 2/25/2021 ABDULLAH SADOZAI

Contact Information

Contractor Your Favorite Contractor Inc; Lic. No.: 851344-B 18375 VENTURA BLVD #402      TARZANA, CA 91356
Engineer Mayorga,, Jose Aguinaldo; Lic. No.: C50322 20457 OREY PL      WINNETKA, CA 91306

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/24/2021 Partial Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 5/27/2021 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 6/17/2021 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 6/24/2021 Approved DANIEL DREW
ELECTRICAL-Rough 7/1/2021 Approved DANIEL DREW
PLUMBING-Rough 7/1/2021 Approved DANIEL DREW
BUILDING-Rough-Frame 7/27/2021 Approved ADAM ESCOTO
Green Building Rough 7/27/2021 Approved ADAM ESCOTO
Insulation 7/27/2021 Approved ADAM ESCOTO
Interior/Exterior Lathing 7/27/2021 Partial Approval ADAM ESCOTO
Shower Pan 7/27/2021 Approved ADAM ESCOTO
Drywall Nailing 7/30/2021 Approved ALAN MORELOS
Interior/Exterior Lathing 7/30/2021 Approved ALAN MORELOS
Final 10/12/2021 Not Ready for Inspection DANIEL DREW
Footing/Foundation/Slab 10/12/2021 Approved DANIEL DREW
Green Building Final 10/12/2021 Approved DANIEL DREW
SGSOV-Seismic Gas S/O Valve 10/12/2021 SGSOV Approved DANIEL DREW
Smoke Detectors 10/12/2021 Approved DANIEL DREW
Final 2/2/2022 OK to Issue CofO CHRISTOPHE COCHRAN