14593 W DEERVALE PL 91403

Certificate Information: 14593 W DEERVALE PL 91403

Application / Permit
20014-20000-05415
Plan Check / Job No.
B20VN15770
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 11'-7" X 16 '-11" ADDITION AND REMODEL TO (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 8/10/2021
Issuing Office
Current Status
CofO Issued on 12/30/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/16/2020 APPLICANT
Assigned to Plan Check Engineer 12/30/2020 RAPHAEL ROSAS
Corrections Issued 1/2/2021 RAPHAEL ROSAS
Plan Check Approved 3/3/2021 RAPHAEL ROSAS
Building Plans Picked Up 3/4/2021 APPLICANT
Issued 8/10/2021 APPLICANT
CofO in Progress 12/9/2021 JACK KARGODORIAN
CofO Issued 12/30/2021 MICHAEL SMITH
Permit Finaled 12/30/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/7/2021 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 1/7/2021 ADRIAN CASTRO
Specific Plan Cleared 2/5/2021 OLGA AYALA
Miscellaneous Cleared 2/18/2021 MIGUEL GAMBOA
ZA Case Cleared 2/18/2021 MIGUEL GAMBOA
ZI Cleared 2/18/2021 MIGUEL GAMBOA
Grading Pre-Inspection Cleared 3/3/2021 RAPHAEL ROSAS

Contact Information

Contractor Owner-Builder       ,
Engineer Sayah,, Daniel Hoshyar; Lic. No.: S6000 15233 VENTURA BLVD 1130      SHERMAN OAKS, CA 91403

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/17/2021 Partial Approval CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 8/25/2021 Corrections Issued CHARLES POWELL
Footing/Foundation/Slab 9/3/2021 Partial Approval CHARLES POWELL
Deputy Drilled-In Anchors 9/7/2021 Approved MICHAEL PELHAM
BUILDING-Rough-Frame 10/12/2021 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 10/12/2021 Approved MISAEL ESPARZA
Green Building Rough 10/12/2021 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 10/18/2021 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 10/18/2021 Approved JACK KARGODORIAN
Green Building Rough 10/18/2021 Approved JACK KARGODORIAN
Insulation 10/18/2021 Approved JACK KARGODORIAN
PLUMBING-Rough 10/18/2021 Approved JACK KARGODORIAN
Drywall Nailing 11/2/2021 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 11/2/2021 Approved ASHLEY THOMPSON
Final 12/9/2021 OK to Issue CofO JACK KARGODORIAN
Footing/Foundation/Slab 12/9/2021 Approved JACK KARGODORIAN
Green Building Final 12/9/2021 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 12/9/2021 SGSOV Approved JACK KARGODORIAN