11020 N VENA AVE 91345
Certificate Information: 11020 N VENA AVE 91345
- Application / Permit
- 20014-20000-05406
- Plan Check / Job No.
- B20VN15752
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD IRREGULAR 20' X 22' TO (E) ACCESSORY DWELLING UNIT W/ ATTACHED RECREATION ROOM, PER GCS 65852.2(E)(1)(B) AND ADD 4' X 8' AND 4' X 15' PATIO COVERS. ALL WORK PER WFPP.
- Permit Issued
- Issued on 2/10/2021
- Issuing Office
- Current Status
- CofO Issued on 10/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/15/2020 | JENNIFER LEE |
| Corrections Issued | 12/16/2020 | JENNIFER LEE |
| Plan Check Approved | 2/10/2021 | JENNIFER LEE |
| Issued | 2/10/2021 | APPLICANT |
| CofO in Progress | 5/5/2021 | JENNIFER RABUCHIN |
| No Progress | 4/7/2022 | MICHAEL TEMPLE |
| CofO in Progress | 9/20/2022 | JENNIFER RABUCHIN |
| CofO Issued | 10/22/2022 | MICHAEL SMITH |
| Permit Finaled | 10/22/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/2/2021 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 2/2/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 2/2/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/2/2021 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 3/3/2021 | Corrections Issued | JENNIFER RABUCHIN |
| METHANE-Barrier | 3/3/2021 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 3/3/2021 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 3/8/2021 | Approved | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 3/19/2021 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 3/19/2021 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2021 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 3/19/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| METHANE-Rough | 3/19/2021 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/1/2021 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 4/1/2021 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/1/2021 | Approved | JENNIFER RABUCHIN |
| MERV13>=Rough | 4/1/2021 | Approved | JENNIFER RABUCHIN |
| Insulation | 4/8/2021 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 4/9/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 5/4/2021 | Approved | JENNIFER RABUCHIN |
| Final | 5/4/2021 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 5/4/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 5/4/2021 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 5/4/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 5/4/2021 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 5/4/2021 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 5/4/2021 | Approved | JENNIFER RABUCHIN |
| Special/Order Compliance | 6/7/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Special/Order Compliance | 9/20/2022 | Approved | JENNIFER RABUCHIN |