12436 W KLING ST 91604
Certificate Information: 12436 W KLING ST 91604
- Application / Permit
- 20014-20000-05394
- Plan Check / Job No.
- B20VN15734
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 18' X 8'2" REAR ADDITION TO (E) SFD TO CREATE A BEDROOM AND NEW BATHROOM, INTERIOR REMODEL TO (E) SFD TO REMODEL LIVING ROOM , DINING ROOM , KITCHEN , BATHROOM , (2) BEDROOMS, CONVERT BEDROOM TO DEN , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 11/3/2021
- Issuing Office
- Current Status
- CofO Issued on 6/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/18/2020 | RARES BODEA |
| Corrections Issued | 12/20/2020 | RARES BODEA |
| Building Plans Picked Up | 12/30/2020 | APPLICANT |
| Plan Check Approved | 5/5/2021 | RARES BODEA |
| Issued | 11/3/2021 | APPLICANT |
| CofO in Progress | 3/16/2022 | ARAM AVEDISIAN |
| CofO Issued | 6/20/2022 | MICHAEL SMITH |
| Permit Finaled | 6/20/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/12/2021 | GUILLERMO PETRA |
| Sewer availability | Cleared | 1/12/2021 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 4/26/2021 | LEE GUILBEAUX |
| ZI | Cleared | 4/27/2021 | PABLO ESTRADA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zolfaghari,, Saeed; Lic. No.: C86761 | 6201 BEE AVE AGOURA HILLS, CA 91301 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/23/2021 | Corrections Issued | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 12/2/2021 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 12/13/2021 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 12/13/2021 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2021 | Partial Approval | ARAM AVEDISIAN |
| Special/Order Compliance | 12/17/2021 | Partial Approval | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 1/4/2022 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Rough | 1/4/2022 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2022 | Approved | JACK KARGODORIAN |
| Green Building Rough | 1/4/2022 | Approved | JACK KARGODORIAN |
| MERV13>=Rough | 1/4/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 1/4/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Rough-Elec/Plmb/HVAC | 1/4/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Wood Frame | 1/4/2022 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 1/11/2022 | Approved | JACK KARGODORIAN |
| Insulation | 1/11/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 1/11/2022 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 1/18/2022 | Approved | ARAM AVEDISIAN |
| Final | 3/2/2022 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 3/2/2022 | Approved | ARAM AVEDISIAN |
| MERV13>=Final | 3/2/2022 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 3/2/2022 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 3/2/2022 | Approved | ARAM AVEDISIAN |
| Final | 3/16/2022 | OK to Issue CofO | ARAM AVEDISIAN |