13147 W BEAVER ST 91342

Certificate Information: 13147 W BEAVER ST 91342

Application / Permit
20014-20000-05387
Plan Check / Job No.
B20VN15702
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
34'-2" X 20' ADDITION TO THE REAR OF EXISTING SINGLE FAMILY DWELLING
Permit Issued
Issued on 10/1/2021
Issuing Office
Current Status
CofO Issued on 4/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/4/2020 APPLICANT
Assigned to Plan Check Engineer 12/18/2020 SELLA BENYAMIN
Corrections Issued 12/22/2020 SELLA BENYAMIN
Building Plans Picked Up 12/30/2020 APPLICANT
Plan Check Approved 10/1/2021 SELLA BENYAMIN
Issued 10/1/2021 APPLICANT
CofO in Progress 3/29/2023 ARAM AVEDISIAN
Permit Finaled 4/19/2023 MICHAEL SMITH
CofO Issued 4/19/2023 MICHAEL SMITH
Permit Finaled 4/19/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/17/2021 MARKOS PEREZ-BRAN
Low Impact Development Cleared 9/20/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 9/21/2021 MARKOS PEREZ-BRAN
Sewer availability Cleared 9/27/2021 CARLOS AGUILERA

Contact Information

Contractor J L General Contractor Inc; Lic. No.: 855007-B 11134 CAYUGA AVENUE      PACOIMA, CA 91331

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/30/2022 Not Ready for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 4/1/2022 Partial Approval JOHN HAYES
Deputy Drilled-In Anchors 4/4/2022 Conditional Approval JOHN HAYES
Excavation/Setback/Form/Re-Bar 4/5/2022 Partial Approval JOHN HAYES
Underground Mechanical 4/5/2022 Approved JOHN HAYES
BUILDING-Rough-Frame 5/19/2022 Corrections Issued JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 5/19/2022 Not Ready for Inspection JOHN HAYES
Green Building Rough 5/19/2022 Not Ready for Inspection JOHN HAYES
Special/Order Compliance 5/23/2022 Corrections Issued MICHAEL TEMPLE
BUILDING-Rough-Frame 6/1/2022 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 6/1/2022 Not Ready for Inspection JOHN HAYES
Green Building Rough 6/1/2022 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 6/7/2022 Corrections Issued JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 6/7/2022 Partial Approval JOHN HAYES
Green Building Rough 6/7/2022 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Rough 6/22/2022 Approved ARAM AVEDISIAN
HVAC-Rough 6/22/2022 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 6/22/2022 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 6/22/2022 Approved ARAM AVEDISIAN
Shower Pan 6/22/2022 Approved ARAM AVEDISIAN
Insulation 6/28/2022 Approved ARAM AVEDISIAN
Drywall Nailing 7/11/2022 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 3/17/2023 Approved ARAM AVEDISIAN
Final 3/17/2023 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 3/17/2023 Approved ARAM AVEDISIAN
Green Building Final 3/17/2023 Approved ARAM AVEDISIAN
Green Building Rough 3/17/2023 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 3/17/2023 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 3/17/2023 Approved ARAM AVEDISIAN
ELECTRICAL-Final 3/29/2023 Approved ARAM AVEDISIAN
Final 3/29/2023 OK to Issue CofO ARAM AVEDISIAN
HVAC-Final 3/29/2023 Approved ARAM AVEDISIAN
PLUMBING-Final 3/29/2023 Approved ARAM AVEDISIAN
Service/Power Release 3/29/2023 Approved ARAM AVEDISIAN