11010 N HASKELL AVE 91344
Certificate Information: 11010 N HASKELL AVE 91344
- Application / Permit
- 20014-20000-05379
- Plan Check / Job No.
- B20VN15693
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 48'8" X 10'1" ADDITION TO THE (E) SFD TO ENLARGE DINING AND LIVING ROOM , ADD ONE BEDROOM AND ONE BATHROOM , INTERIOR REMODEL TO (E) SFD TO REMODEL DINING AND LIVING ROOM AND ADD ONE BEDROOM, REMODEL KITCHEN , NEW LAUNDRY AND NEW CLOSETS , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 5/13/2022
- Issuing Office
- Current Status
- CofO Issued on 1/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/18/2020 | RARES BODEA |
| Corrections Issued | 12/22/2020 | RARES BODEA |
| Applicant returned to address corrections | 3/29/2022 | RARES BODEA |
| Applicant returned to address corrections | 5/3/2022 | DANIEL ABRAMYAN |
| Building Plans Picked Up | 5/3/2022 | APPLICANT |
| Applicant returned to address corrections | 5/11/2022 | RARES BODEA |
| Plan Check Approved | 5/13/2022 | RARES BODEA |
| Issued | 5/13/2022 | APPLICANT |
| CofO in Progress | 12/26/2024 | JAVIER RAMOS JR |
| CofO in Progress | 12/26/2024 | JAVIER RAMOS JR |
| CofO in Progress | 12/26/2024 | JAVIER RAMOS JR |
| Permit Finaled | 1/3/2025 | RUBEN SALAS |
| CofO Issued | 1/3/2025 | RUBEN SALAS |
| Permit Finaled | 1/3/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Sewer availability | Cleared | 3/26/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 4/1/2021 | ADRIAN CASTRO |
| ZA Case | Cleared | 10/12/2021 | KENTON TRINH |
| Low Impact Development | Cleared | 4/25/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 4/28/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/9/2022 | Conditional Approval | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 8/29/2022 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2022 | Partial Approval | DEANDRE HOFFMAN |
| Wood Frame | 11/23/2022 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 1/24/2023 | Corrections Issued | ROBERT GOLD |
| Gas Test | 1/24/2023 | Approved | ROBERT GOLD |
| HVAC-Rough | 1/24/2023 | Approved | ROBERT GOLD |
| Interior/Exterior Lathing | 1/24/2023 | Partial Approval | ROBERT GOLD |
| PLUMBING-Rough | 1/24/2023 | Corrections Issued | ROBERT GOLD |
| Wood Frame | 1/24/2023 | Corrections Issued | ROBERT GOLD |
| Deputy Wood Construction | 1/27/2023 | Conditional Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 1/31/2023 | Approved | JOHN COLEMAN |
| Insulation | 1/31/2023 | Approved | JOHN COLEMAN |
| PLUMBING-Rough | 1/31/2023 | Approved | JOHN COLEMAN |
| Shower Pan | 1/31/2023 | Approved | JOHN COLEMAN |
| Wood Frame | 1/31/2023 | Approved | JOHN COLEMAN |
| Drywall Nailing | 2/13/2023 | Approved | JAVIER RAMOS JR |
| Gas Test | 2/13/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Rough | 2/13/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 2/13/2023 | Approved | JAVIER RAMOS JR |
| Shower Pan | 2/13/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 4/27/2023 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 4/27/2023 | Approved | JAVIER RAMOS JR |
| Final | 4/27/2023 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 4/27/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 4/27/2023 | Approved | JAVIER RAMOS JR |
| MERV13>=Final | 4/27/2023 | Approved | JAVIER RAMOS JR |
| MERV13>=Rough | 4/27/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 4/27/2023 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 4/27/2023 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 4/27/2023 | Approved | JAVIER RAMOS JR |
| Final | 12/26/2024 | OK to Issue CofO | JAVIER RAMOS JR |