23056 W BALTAR ST 91304
Certificate Information: 23056 W BALTAR ST 91304
- Application / Permit
- 20014-20000-05349
- Plan Check / Job No.
- B20VN15659
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ECPC: 495 SQ. FT. ADDITION OF A MASTER BEDROOM, MASTER BATHROOM, WALK IN CLOSET AND LAUNDRY ROOM. CONVERT THE (E) CLOSET INTO A NEW BEDROOM.
- Permit Issued
- Issued on 4/19/2021
- Issuing Office
- Current Status
- Issued on 4/19/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/18/2020 | JESSE ARELLANO |
| Corrections Issued | 1/13/2021 | JESSE ARELLANO |
| Plan Check Approved | 4/18/2021 | JESSE ARELLANO |
| Issued | 4/19/2021 | APPLICANT |
| Building Plans Picked Up | 4/19/2021 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/30/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 12/30/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 2/17/2021 | JEREMY CARTER |
| Low Impact Development | Cleared | 4/14/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 4/14/2021 | ABDULLAH SADOZAI |
| Green Code | Cleared | 4/18/2021 | JESSE ARELLANO |
Contact Information
| Contractor | C I D Builders And Developers Inc; Lic. No.: 958193-B | 4804 LAUREL CYN BLVD #755 STUDIO CITY, CA 91607 |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 8916 LONGDON AVE #C TEMPLE CITY, CA 91780 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/25/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Footing/Foundation/Slab | 7/1/2021 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Rough | 7/1/2021 | Corrections Issued | DAVID STEPANYAN |
| Sewer | 7/1/2021 | Approved | DAVID STEPANYAN |
| Sewer | 7/7/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Footing/Foundation/Slab | 7/12/2021 | Approved | DAVID STEPANYAN |
| PLUMBING-Rough | 7/12/2021 | Partial Approval | DAVID STEPANYAN |
| Wood Frame | 8/4/2021 | Corrections Issued | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2021 | Partial Approval | HENRY KIM |
| BUILDING-Rough-Frame | 10/7/2021 | Corrections Issued | DAVID STEPANYAN |
| ELECTRICAL-Rough | 10/7/2021 | Approved | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2021 | Partial Approval | DAVID STEPANYAN |
| Green Building Rough | 10/7/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| PLUMBING-Rough | 10/7/2021 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 10/13/2021 | Not Ready for Inspection | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2021 | Corrections Issued | HENRY KIM |
| Green Building Rough | 10/13/2021 | Not Ready for Inspection | HENRY KIM |
| BUILDING-Rough-Frame | 10/20/2021 | Approved | DAVID STEPANYAN |
| Green Building Rough | 10/20/2021 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 10/20/2021 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 10/20/2021 | Partial Approval | DAVID STEPANYAN |
| Insulation | 10/26/2021 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 10/26/2021 | Partial Approval | JESUS PINEDA |
| Drywall Nailing | 10/29/2021 | Approved | JESUS PINEDA |
| Shower Pan | 10/29/2021 | Not Ready for Inspection | JESUS PINEDA |
| Interior/Exterior Lathing | 11/4/2021 | Approved | DAVID STEPANYAN |
| Shower Pan | 11/4/2021 | Approved | DAVID STEPANYAN |
| Final | 2/1/2022 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 2/1/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 2/1/2022 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 2/1/2022 | Approved | DAVID SCANTLIN |