13824 W LA MAIDA ST 91423

Certificate Information: 13824 W LA MAIDA ST 91423

Application / Permit
20014-20000-05309
Plan Check / Job No.
B20VN15558
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
25'-6" X 12'-3"ADDITION TO EXTEND BEDROOM AND NEW BATHROOM. INTERIOR REMODEL AT (E) BEDROOM AND BATHROOM. WORK PER ENGINEER.
Permit Issued
Issued on 2/18/2021
Issuing Office
Current Status
CofO Issued on 8/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/2/2020 APPLICANT
Assigned to Plan Check Engineer 12/9/2020 ROSENDO MEDINA
Corrections Issued 12/12/2020 ROSENDO MEDINA
Plan Check Approved 2/1/2021 ROSENDO MEDINA
Issued 2/18/2021 APPLICANT
CofO in Progress 9/16/2021 MISAEL ESPARZA
Permit Finaled 8/3/2022 DANIEL ORRANTE
CofO Issued 8/3/2022 DANIEL ORRANTE
Permit Finaled 8/3/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/28/2020 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 12/28/2020 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 12/28/2020 LEE GUILBEAUX
Public Works-Sewers Cleared 12/28/2020 LEE GUILBEAUX

Contact Information

Contractor Orbell Construction Corporation; Lic. No.: 523341-B 2933 OAKMONT VIEW DRIVE      GLENDALE, CA 91208
Engineer Arakelyan,, Aram; Lic. No.: C82796 145 S GLENOAKS BI 328      BURBANK, CA 91502

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/18/2021 Approved CHARLES POWELL
Footing/Foundation/Slab 3/18/2021 Approved CHARLES POWELL
PLUMBING-Rough 3/26/2021 Partial Approval DANIEL DREW
Insulation 4/1/2021 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 5/3/2021 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 5/6/2021 Approved CHARLES POWELL
HVAC-Rough 5/6/2021 Approved CHARLES POWELL
PLUMBING-Rough 5/6/2021 Not Ready for Inspection CHARLES POWELL
BUILDING-Rough-Frame 5/12/2021 Approved CHARLES POWELL
Green Building Rough 5/12/2021 Not Ready for Inspection CHARLES POWELL
MERV13>=Rough 5/12/2021 Approved CHARLES POWELL
PLUMBING-Rough 5/12/2021 Approved CHARLES POWELL
Interior/Exterior Lathing 5/17/2021 Partial Approval JOHN HAYES
Insulation 5/19/2021 Approved JAVIER RAMOS JR
Drywall Nailing 5/26/2021 Not Ready for Inspection JUSTIN HAWLEY
Drywall Nailing 6/1/2021 Approved ALAN MORELOS
Interior/Exterior Lathing 6/1/2021 Approved ALAN MORELOS
BUILDING-Rough-Frame 8/24/2021 Approved CHARLES POWELL
ELECTRICAL-Final 8/24/2021 Corrections Issued CHARLES POWELL
Final 8/24/2021 Corrections Issued CHARLES POWELL
Green Building Final 8/24/2021 Approved CHARLES POWELL
Green Building Rough 8/24/2021 Approved CHARLES POWELL
HVAC-Final 8/24/2021 Corrections Issued CHARLES POWELL
MERV13>=Final 8/24/2021 Approved CHARLES POWELL
PLUMBING-Final 8/24/2021 Not Ready for Inspection CHARLES POWELL
SGSOV-Seismic Gas S/O Valve 8/24/2021 SGSOV Approved CHARLES POWELL
Smoke Detectors 8/24/2021 Approved CHARLES POWELL
ELECTRICAL-Final 9/15/2021 Approved MISAEL ESPARZA
Final 9/15/2021 OK to Issue CofO MISAEL ESPARZA
HVAC-Final 9/15/2021 Approved MISAEL ESPARZA
PLUMBING-Final 9/15/2021 Approved MISAEL ESPARZA