4961 N AGNES AVE 91607
Certificate Information: 4961 N AGNES AVE 91607
- Application / Permit
- 20014-20000-05296
- Plan Check / Job No.
- B20VN15550
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT TO LIVING SPACE AND ENCLOSE (E) 5'X 19'10" PORTION OF (E) PATIO COVER AT (E) SFD TO ENLARGE THE BEDROOM , CONVERT 20'5" X 18'6" DETACHED GARAGE TO NEW MASTER BEDROOM AND (2) BATHROOMS AND ADD 28'6"X 26'3"IRREGULAR SHAPED ADDITION TO ATTACH GARAGE TO (E) SFD AND TO CREATE NEW BEDROOM , PANTRY AND W.I.C., INTERIOR REMODEL TO (E) SFD TO REMODEL (2) BEDROOMS , (2) BATHROOMS , LAUNDRY , KITCHEN , LIVING , DINING ,NFPA-13D FIRE SPRINKLERS REQUIRED, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 1/31/2022
- Issuing Office
- Current Status
- CofO Issued on 7/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2020 | RARES BODEA |
| Corrections Issued | 1/3/2021 | RARES BODEA |
| Quality Review Completed | 1/7/2021 | STEVEN KIM |
| Building Plans Picked Up | 1/7/2021 | APPLICANT |
| Applicant returned to address corrections | 11/22/2021 | RARES BODEA |
| Plan Check Approved | 1/31/2022 | RARES BODEA |
| Issued | 1/31/2022 | APPLICANT |
| CofO in Progress | 6/2/2023 | JACK KARGODORIAN |
| Permit Finaled | 7/25/2023 | DANIEL ORRANTE |
| CofO Issued | 7/25/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/25/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 2/16/2021 | ERIN NASH |
| ZI | Cleared | 2/16/2021 | ERIN NASH |
| ZI | Cleared | 2/16/2021 | ERIN NASH |
| Hydrant and Access approval | Cleared | 4/2/2021 | JOHN CONNEALLY |
| Eng Process Fee Ord 176,300 | Cleared | 5/5/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 5/5/2021 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 10/13/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 10/14/2021 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zolfaghari,, Saeed; Lic. No.: C86761 | 6201 BEE AVE AGOURA HILLS, CA 91301 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/2/2022 | Approved | THOMAS FINNILA |
| Footing/Foundation/Slab | 3/7/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 3/15/2022 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 3/16/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 4/4/2022 | Corrections Issued | THOMAS FINNILA |
| BUILDING-Rough-Frame | 5/13/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Rough | 5/13/2022 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 5/19/2022 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 5/19/2022 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 5/24/2022 | Partial Approval | DAVID MATSON |
| PLUMBING-Rough | 5/24/2022 | Partial Approval | DAVID MATSON |
| Pre-Inspection | 5/24/2022 | Not Ready for Inspection | DAVID MATSON |
| Insulation | 5/27/2022 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2022 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2022 | Corrections Issued | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 9/6/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2022 | Partial Approval | DEANDRE HOFFMAN |
| Green Building Rough | 9/6/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| PLUMBING-Rough | 9/6/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 9/26/2022 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 9/26/2022 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 10/12/2022 | Approved | ROBERT GOLD |
| BUILDING-Rough-Frame | 10/21/2022 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 10/21/2022 | Approved | JACK KARGODORIAN |
| Green Building Rough | 10/21/2022 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 10/21/2022 | Corrections Issued | JACK KARGODORIAN |
| Insulation | 10/27/2022 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 11/3/2022 | Approved | JACK KARGODORIAN |
| Shower Pan | 11/3/2022 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 11/7/2022 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 11/7/2022 | Partial Approval | JACK KARGODORIAN |
| Final | 2/3/2023 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 2/3/2023 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 2/3/2023 | SGSOV Not Ready | JACK KARGODORIAN |
| Smoke Detectors | 2/3/2023 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 3/7/2023 | SGSOV Not Ready | JACK KARGODORIAN |
| Final | 5/15/2023 | Corrections Issued | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 5/15/2023 | SGSOV Not Ready | JACK KARGODORIAN |
| Final | 5/23/2023 | Corrections Issued | JACK KARGODORIAN |
| Final | 6/1/2023 | OK to Issue CofO | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 6/1/2023 | SGSOV Approved | JACK KARGODORIAN |
| Service/Power Release | 6/1/2023 | Approved | JACK KARGODORIAN |