3350 N SUNNYNOOK DR 90039

Certificate Information: 3350 N SUNNYNOOK DR 90039

Application / Permit
20014-20000-05284
Plan Check / Job No.
B20VN15519
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD IRREGULAR 10'-6" X 12'-9" TO EXPAND (E) BATHROOM, NEW LAUNDRY/HALLWAY, REMOVE INTERIOR WALLS AT (E) KITCHEN/DINING ROOM AND REPLACE WITH NEW BEAMS, REMODEL (E) BATHROOM/BEDROOMS. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 1/5/2021
Issuing Office
Current Status
CofO Issued on 5/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/1/2020 APPLICANT
Assigned to Plan Check Engineer 12/9/2020 JENNIFER LEE
Corrections Issued 12/10/2020 JENNIFER LEE
Plan Check Approved 1/5/2021 JENNIFER LEE
Issued 1/5/2021 APPLICANT
CofO in Progress 4/21/2021 HAMIK HARTOUNIAN
Permit Finaled 5/1/2021 DEROLD HAUFF
CofO Issued 5/1/2021 DEROLD HAUFF
Permit Finaled 5/1/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/28/2020 ROSA SILVA
Roof/Waste drainage to street Cleared 12/28/2020 ROSA SILVA

Contact Information

Contractor Owner-Builder       ,
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/11/2021 No Access for Inspection ELMER BLAND
Excavation/Setback/Form/Re-Bar 1/11/2021 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 1/11/2021 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 1/22/2021 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 1/26/2021 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 1/29/2021 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 2/5/2021 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 2/5/2021 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 2/5/2021 Approved HAMIK HARTOUNIAN
Green Building Rough 2/5/2021 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 2/5/2021 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 2/5/2021 Approved HAMIK HARTOUNIAN
Drywall Nailing 2/16/2021 Approved HAMIK HARTOUNIAN
Green Building Rough 2/16/2021 Approved HAMIK HARTOUNIAN
Insulation 2/16/2021 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 2/16/2021 Approved HAMIK HARTOUNIAN
Final 3/26/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Final 3/26/2021 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 3/26/2021 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 3/26/2021 Approved HAMIK HARTOUNIAN
Final 4/9/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Gas Test 4/9/2021 Approved HAMIK HARTOUNIAN
Green Building Final 4/9/2021 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 4/9/2021 SGSOV Not Ready HAMIK HARTOUNIAN
Final 4/20/2021 OK to Issue CofO HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 4/20/2021 SGSOV Approved HAMIK HARTOUNIAN