11043 W CALIFA ST 91601

Certificate Information: 11043 W CALIFA ST 91601

Application / Permit
20014-20000-05278
Plan Check / Job No.
B20VN15497
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18' X 20' DETACHED GARAGE AND ADD IRREGULAR 31'-8" X 37'-6" FOR (N) ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(C) AND (D). ALL WORK PER WFPP.
Permit Issued
Issued on 11/10/2021
Issuing Office
Current Status
CofO Issued on 8/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/2/2020 APPLICANT
Assigned to Plan Check Engineer 12/15/2020 JENNIFER LEE
Corrections Issued 12/17/2020 JENNIFER LEE
Applicant returned to address corrections 10/26/2021 JENNIFER LEE
Plan Check Approved 11/9/2021 JENNIFER LEE
Issued 11/10/2021 APPLICANT
Building Plans Picked Up 11/12/2021 APPLICANT
CofO in Progress 8/17/2022 JOHN HAYES
CofO Issued 8/24/2022 DANIEL ORRANTE
Permit Finaled 8/24/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 1/4/2021 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 1/5/2021 GUILLERMO PETRA
Sewer availability Cleared 1/5/2021 GUILLERMO PETRA
Low Impact Development Cleared 5/21/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 8/10/2021 DAGOVERTO GUERRERO
Construction near power lines Cleared 10/21/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/1/2022 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 2/4/2022 Approved RICHARD DOCKUS
Sewer 2/4/2022 Approved RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 2/23/2022 Partial Approval CALEB MEISTER
Green Building Rough 2/23/2022 Not Ready for Inspection CALEB MEISTER
Interior/Exterior Lathing 2/23/2022 Not Ready for Inspection CALEB MEISTER
BUILDING-Rough-Frame 3/8/2022 Corrections Issued MATT KELLERMAN
ELECTRICAL-Rough 3/8/2022 Partial Approval MATT KELLERMAN
HVAC-Rough 3/8/2022 Conditional Approval MATT KELLERMAN
PLUMBING-Rough 3/8/2022 Corrections Issued MATT KELLERMAN
BUILDING-Rough-Frame 3/15/2022 Approved Pending GreenApproval ARAM AVEDISIAN
ELECTRICAL-Rough 3/15/2022 Approved ARAM AVEDISIAN
Green Building Rough 3/15/2022 Approved ARAM AVEDISIAN
HVAC-Rough 3/15/2022 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 3/15/2022 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 3/15/2022 Approved ARAM AVEDISIAN
Insulation 3/18/2022 Approved CALEB MEISTER
Shower Pan 3/18/2022 Approved CALEB MEISTER
Drywall Nailing 3/30/2022 Approved CALEB MEISTER
ELECTRICAL-Final 6/2/2022 Corrections Issued ARAM AVEDISIAN
HVAC-Final 6/2/2022 Approved ARAM AVEDISIAN
PLUMBING-Final 6/2/2022 Approved ARAM AVEDISIAN
ELECTRICAL-Final 7/19/2022 Approved JOHN HAYES
Final 7/19/2022 Corrections Issued JOHN HAYES
BUILDING-Rough-Frame 8/16/2022 Approved JOHN HAYES
Final 8/16/2022 OK to Issue CofO JOHN HAYES
Green Building Final 8/16/2022 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 8/16/2022 SGSOV Approved JOHN HAYES
Service/Power Release 8/16/2022 Approved JOHN HAYES
Smoke Detectors 8/16/2022 Approved JOHN HAYES