5033 N VANALDEN AVE 91356

Certificate Information: 5033 N VANALDEN AVE 91356

Application / Permit
20014-20000-05275
Plan Check / Job No.
B20VN15464
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ENCLOSE EXISTING COVERED PATIO (APRROX 7' X 14'-2" IRREGULAR SHAPED) TO ENLARGE EXISTING BEDROOM; INTERIOR REMODEL; REMOVE AND REPLACE WINDOWS AND DOORS
Permit Issued
Issued on 1/7/2021
Issuing Office
Current Status
CofO Issued on 9/28/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/30/2020 APPLICANT
Assigned to Plan Check Engineer 12/11/2020 SELLA BENYAMIN
Corrections Issued 12/15/2020 SELLA BENYAMIN
Building Plans Picked Up 12/15/2020 APPLICANT
Issued 1/7/2021 APPLICANT
Permit Finaled-Status Void 9/15/2021 DAVID SANDOVAL
Re-Activate Permit 9/23/2021 DAVID SANDOVAL
CofO in Progress 9/28/2021 DAVID SANDOVAL
CofO Issued 9/28/2021 MICHAEL SMITH
Permit Finaled 9/28/2021 MICHAEL SMITH

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Eskandarian Rafee; Lic. No.: 893662-B 3125 EVELYN ST      LA CRESCENTA, CA 91214
Engineer Tan,, Henreik Steven; Lic. No.: C65723 5100 LLANO DRIVE      WOODLAND HILLS, CA 91364

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/13/2021 Partial Approval CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 1/15/2021 Partial Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 2/3/2021 Partial Approval DAVID SANDOVAL
PLUMBING-Rough 3/3/2021 Partial Approval DAVID SANDOVAL
HVAC-Rough 3/15/2021 Corrections Issued DAVID SANDOVAL
PLUMBING-Rough 3/16/2021 Corrections Issued DAVID SANDOVAL
ELECTRICAL-Rough 3/25/2021 Corrections Issued DAVID SANDOVAL
ELECTRICAL-Rough 4/8/2021 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 4/14/2021 Approved DAVID SANDOVAL
Green Building Rough 4/14/2021 Approved DAVID SANDOVAL
Insulation 4/14/2021 Approved DAVID SANDOVAL
Interior/Exterior Lathing 4/14/2021 Partial Approval DAVID SANDOVAL
Drywall Nailing 4/22/2021 Approved DAVID SANDOVAL
Shower Pan 5/18/2021 Approved LILIANA PORTILLO
ELECTRICAL-Final 8/9/2021 Not Ready for Inspection DAVID SANDOVAL
HVAC-Final 8/9/2021 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Final 8/9/2021 Not Ready for Inspection DAVID SANDOVAL
Gas Test 8/23/2021 Approved RYAN SALAZAR
ELECTRICAL-Final 8/31/2021 Approved DAVID SANDOVAL
Final 8/31/2021 Corrections Issued DAVID SANDOVAL
HVAC-Final 8/31/2021 Approved DAVID SANDOVAL
PLUMBING-Final 8/31/2021 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 8/31/2021 SGSOV Not Ready DAVID SANDOVAL
Smoke Detectors 8/31/2021 Approved DAVID SANDOVAL
Final 9/15/2021 Partial Approval DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 9/15/2021 SGSOV Approved DAVID SANDOVAL
Final 9/28/2021 OK to Issue CofO DAVID SANDOVAL