ENCLOSE 13'11" X 3' 2ND FLOOR WALL OVERHANG AT 1ST FLOOR TO ENLARGE THE FAMILY ROOM , NEW 24'3" X 14'4" 2ND FLOOR ADDITION TO (E) SFD TO CREATE NEW BEDROOM , NEW MASTER BATHROOM ,NEW 9' X 14' REAR OPEN TRELLIS , INTERIOR REMODEL TO (E) SFD TO REMODEL REMODEL FAMILY ROOM , BEDROOM , KITCHEN , DINING ROOM , LIVING ROOM AT 1ST FLOOR , REMODEL (2) BEDROOMS , (1) BATHROOM , MASTER CLOSET , REMOVE (1) BEDROOM AT 2ND FLOOR, ADD SKYLIGHT , WINDOWS & DOORS REPLACEMENT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 3/18/2021
Issuing Office
Current Status
CofO Issued on 9/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/30/2020 APPLICANT
Assigned to Plan Check Engineer 12/23/2020 RARES BODEA
Corrections Issued 12/27/2020 RARES BODEA
Quality Review Completed 12/31/2020 STEVEN KIM
Building Plans Picked Up 1/4/2021 APPLICANT
Applicant returned to address corrections 3/15/2021 RARES BODEA
Plan Check Approved 3/18/2021 RARES BODEA
Issued 3/18/2021 APPLICANT
CofO in Progress 8/31/2023 ARAM AVEDISIAN
Permit Finaled 9/9/2023 DANIEL ORRANTE
CofO Issued 9/9/2023 DANIEL ORRANTE
Permit Finaled 9/9/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/14/2021 DINAH GARIN
Roof/Waste drainage to street Cleared 1/14/2021 DINAH GARIN
Sewer availability Cleared 1/14/2021 DINAH GARIN
Hydrant and Access approval Cleared 3/3/2021 KURT CORRAL
Grading Pre-Inspection Cleared 3/15/2021 RARES BODEA

Contact Information

Contractor Owner-Builder       ,
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/20/2021 Approved ROBERT SHELLY
Footing/Foundation/Slab 4/23/2021 Conditional Approval JOHN KIDWELL
BUILDING-Rough-Frame 8/16/2021 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 8/16/2021 Partial Approval JOHN KIDWELL
Green Building Rough 8/16/2021 Not Ready for Inspection JOHN KIDWELL
Rough-Elec/Plmb/HVAC 8/16/2021 Approved JOHN KIDWELL
BUILDING-Rough-Frame 9/23/2021 Corrections Issued ANDREW NAVE
HVAC-Rough 9/23/2021 Approved ANDREW NAVE
Insulation 9/23/2021 Partial Inspection ANDREW NAVE
Interior/Exterior Lathing 9/23/2021 Not Ready for Inspection ANDREW NAVE
Special/Order Compliance 9/23/2021 Partial Approval JESUS RODRIGUEZ
BUILDING-Rough-Frame 9/30/2021 Approved JOHN KIDWELL
Green Building Rough 9/30/2021 Approved JOHN KIDWELL
Interior/Exterior Lathing 9/30/2021 Approved JOHN KIDWELL
Drywall Nailing 10/5/2021 Approved JOHN KIDWELL
Service/Power Release 10/20/2021 Approved JOHN KIDWELL
Special/Order Compliance 10/21/2021 Partial Inspection JOHN KIDWELL
Final 8/2/2023 Corrections Issued OGANES TARAKHCHYAN
Footing/Foundation/Slab 8/2/2023 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 8/2/2023 SGSOV Approved OGANES TARAKHCHYAN
Final 8/30/2023 OK to Issue CofO ARAM AVEDISIAN
Green Building Final 8/30/2023 Approved ARAM AVEDISIAN
Smoke Detectors 8/30/2023 Approved ARAM AVEDISIAN