13706 N GLENOAKS BLVD 91342

Certificate Information: 13706 N GLENOAKS BLVD 91342

Application / Permit
20014-20000-05266
Plan Check / Job No.
B20VN15449
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
18' X 17' ADDITION TO (E) ACCESSORY LIVING QUARTERS FOR NEW BEDROOM AND BATHROOM.
Permit Issued
Issued on 1/8/2021
Issuing Office
Current Status
CofO Issued on 6/28/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/30/2020 APPLICANT
Assigned to Plan Check Engineer 12/4/2020 ROSENDO MEDINA
Corrections Issued 12/5/2020 ROSENDO MEDINA
Plan Check Approved 1/8/2021 JEROME MAGAT PALMA
Issued 1/8/2021 APPLICANT
CofO in Progress 5/26/2021 MISAEL ESPARZA
Permit Finaled 6/28/2021 MICHAEL SMITH
CofO Issued 6/28/2021 MICHAEL SMITH
Permit Finaled 6/28/2021 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/18/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 12/21/2020 GUILLERMO PETRA
Sewer availability Cleared 12/21/2020 GUILLERMO PETRA

Contact Information

Contractor Aligned Construction Company Inc; Lic. No.: 894983-B 8905 GLENOAKS BLVD UNIT L      SUN VALLEY, CA 91352

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/20/2021 No Result Entered KENNETH KUROWSKI
Footing/Foundation/Slab 1/22/2021 Not Ready for Inspection MICHAEL TEMPLE
PLUMBING-Rough 1/22/2021 Corrections Issued MICHAEL TEMPLE
PLUMBING-Rough 1/26/2021 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 1/28/2021 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 3/2/2021 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 3/2/2021 Approved MISAEL ESPARZA
Green Building Rough 3/2/2021 Not Ready for Inspection MISAEL ESPARZA
MERV13>=Rough 3/2/2021 Approved MISAEL ESPARZA
PLUMBING-Rough 3/2/2021 Corrections Issued MISAEL ESPARZA
Shower Pan 3/2/2021 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 3/12/2021 Corrections Issued MISAEL ESPARZA
Green Building Rough 3/12/2021 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 3/12/2021 Partial Approval MISAEL ESPARZA
Shower Pan 3/12/2021 Corrections Issued MISAEL ESPARZA
Insulation 3/31/2021 Approved MISAEL ESPARZA
Interior/Exterior Lathing 3/31/2021 Partial Approval MISAEL ESPARZA
Wood Frame 3/31/2021 Approved MISAEL ESPARZA
Drywall Nailing 4/9/2021 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 4/9/2021 Approved JOAQUIN GREENOUGH
Sewer 4/14/2021 Approved MISAEL ESPARZA
Shower Pan 4/14/2021 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 5/17/2021 SGSOV Not Ready MISAEL ESPARZA
Final 5/20/2021 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 5/25/2021 Approved MISAEL ESPARZA
ELECTRICAL-Final 5/25/2021 Approved MISAEL ESPARZA
Final 5/25/2021 OK to Issue CofO MISAEL ESPARZA
Green Building Final 5/25/2021 Approved MISAEL ESPARZA
Green Building Rough 5/25/2021 Approved MISAEL ESPARZA
HVAC-Final 5/25/2021 Approved MISAEL ESPARZA
MERV13>=Final 5/25/2021 Approved MISAEL ESPARZA
PLUMBING-Final 5/25/2021 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 5/25/2021 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 5/25/2021 Approved MISAEL ESPARZA