13800 W ROSCOE BLVD 91402
Certificate Information: 13800 W ROSCOE BLVD 91402
- Application / Permit
- 20014-20000-05265
- Plan Check / Job No.
- B20VN15448
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (9) Car Wash
- Work Description
- ADDITION TO (E) CARWASH STRUCTURE;RESTRIPE PARKING LOT
- Permit Issued
- Issued on 8/15/2022
- Issuing Office
- Metro
- Current Status
- Issued on 8/15/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2020 | SELLA BENYAMIN |
| Corrections Issued | 12/14/2020 | SELLA BENYAMIN |
| Quality Review Completed | 12/18/2020 | STEVEN KIM |
| Building Plans Picked Up | 12/18/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 12/18/2020 | APPLICANT |
| Green Plans Picked Up | 12/18/2020 | APPLICANT |
| Applicant returned to address corrections | 12/3/2021 | SELLA BENYAMIN |
| Applicant returned to address corrections | 4/1/2022 | SELLA BENYAMIN |
| Applicant returned to address corrections | 5/5/2022 | SELLA BENYAMIN |
| Plan Check Approved | 8/4/2022 | SELLA BENYAMIN |
| Issued | 8/15/2022 | APPLICANT |
| TCO Issued (Expire Date: 01-26-2026) | 7/30/2025 | RICKEY JACKSON |
| TCO Issued (Expire Date: 07-05-2026) | 1/6/2026 | JEFFREY DURAN |
Permit Application Clearance Information
| DAS Clearance | Cleared | 1/28/2021 | SELLA BENYAMIN |
| Green Code | Cleared | 1/28/2021 | MICHAEL AYERS |
| "Q" conditions | Cleared | 2/2/2021 | DANG NGUYEN |
| Automotive Use | Cleared | 3/23/2021 | NOAH MCCOY |
| Automotive Use | Cleared | 3/23/2021 | NOAH MCCOY |
| Comm Cor/Mini-Mall | Cleared | 3/23/2021 | NOAH MCCOY |
| Comm Cor/Mini-Mall | Cleared | 3/23/2021 | NOAH MCCOY |
| Comm Cor/Mini-Mall | Cleared | 3/23/2021 | NOAH MCCOY |
| Prkng lot landscape/Water mgmt | Cleared | 3/23/2021 | NOAH MCCOY |
| Address approval | Cleared | 5/20/2021 | ADRIAN CASTRO |
| Address approval | Cleared | 5/20/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2021 | LEE GUILBEAUX |
| Highway dedication | Cleared | 10/7/2021 | CARLOS AGUILERA |
| Driveway location | Cleared | 10/13/2021 | DURRE SHAMSI |
| Sewer availability | Cleared | 3/4/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 3/9/2022 | IDA MEISAMI-FARD |
| Roof/Waste drainage to street | Cleared | 3/15/2022 | CARLOS AGUILERA |
| Miscellaneous | Cleared | 5/19/2022 | NOAH MCCOY |
Contact Information
| Contractor | Diamond West Builders; Lic. No.: 921003-B | 2907 E FIRECREST CT ONTARIO, CA 91761 |
| Engineer | Rahman,, Moksudur; Lic. No.: C69263 | 14616 MCKENDREE AVE CHINO, CA 91708 |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/31/2022 | Not Ready for Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 11/3/2022 | Not Ready for Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 11/9/2022 | Not Ready for Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 11/17/2022 | Approved | ANDREW DORSO |
| Green Building Rough | 12/23/2022 | Not Ready for Inspection | ANDREW DORSO |
| Wood Frame | 12/23/2022 | Partial Inspection | ANDREW DORSO |
| Green Building Rough | 3/20/2023 | Not Ready for Inspection | ANDREW DORSO |
| Interior/Exterior Lathing | 3/20/2023 | Not Ready for Inspection | ANDREW DORSO |
| Wood Frame | 3/20/2023 | Not Ready for Inspection | ANDREW DORSO |
| Green Building Rough | 3/23/2023 | Approved | ANDREW DORSO |
| Interior/Exterior Lathing | 3/23/2023 | Approved | ANDREW DORSO |
| Wood Frame | 3/23/2023 | Partial Inspection | ANDREW DORSO |
| Insulation | 3/28/2023 | Approved | ANDREW DORSO |
| Drywall Nailing | 4/3/2023 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 6/7/2023 | Partial Inspection | ANDREW DORSO |
| Wall Anchors | 8/21/2023 | Approved | ANDREW DORSO |
| Wood Frame | 8/21/2023 | Approved | ANDREW DORSO |
| Drywall Nailing | 8/23/2023 | Approved | ANDREW DORSO |
| Final | 11/6/2023 | Partial Inspection | ANDREW DORSO |
| Green Building Final | 11/6/2023 | Approved | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 11/6/2023 | SGSOV Not Ready | ANDREW DORSO |
| Smoke Detectors | 11/6/2023 | Not Ready for Inspection | ANDREW DORSO |
| Masonry Wall/Backfill | 3/5/2024 | Partial Inspection | ANDREW DORSO |
| Masonry Wall/Backfill | 3/19/2024 | Not Ready for Inspection | ANDREW DORSO |
| Final | 6/6/2025 | Not Ready for Inspection | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 6/6/2025 | SGSOV Approved | ANDREW DORSO |
| Smoke Detectors | 6/6/2025 | Approved | ANDREW DORSO |
| Final | 7/15/2025 | Partial Inspection | ANDREW DORSO |
| Special/Order Compliance | 12/29/2025 | Partial Inspection | ANDREW DORSO |
| Special/Order Compliance | 1/6/2026 | Partial Approval | ANDREW DORSO |